Grenfell Tower Inquiry recommendations: progress update - March 2026
The progress update contains information regarding the Grenfell Tower Inquiry recommendations (so far as relevant to Scotland). Information is current up until 1 March 2026. Further progress updates will follow in due course.
Theme - Government and restructuring
Recommendation 3 - Fire Safety Regulatory Unification
Reserved area – No
Delivery – Guidance
Target date – 28/02/2026
Activity since last update
Although this recommendation is primarily directed at the UK Government, the Scottish Government has reviewed the function, operation, remit and membership of the Ministerial Working Group on Building & Fire Safety, to ensure that it can operate effectively and efficiently in proactively, as well as reactively, considering issues related to building & fire safety.
Planned activity
Although the initial review is complete, we will continue to ensure the Group has an appropriate membership and remit. A further review will take place after the Scottish Parliament election.
Further information - Ministerial Working Group on Building & Fire Safety.
Recommendation 4 - Chief Construction Adviser Appointment
Reserved area – No
Delivery – Guidance
Target date – 31/03/2029
Activity since last update
1. Mapping of the construction policy landscape across Scottish Government to identify interfaces, regulatory responsibilities and potential overlaps.
2. Development of an outline brief to support procurement of a specialist consultant to undertake an options appraisal; including early, high level, options that will be explored in more detail during the appraisal.
3. Continued development of the programme and implementation plan for this recommendation.
4. Engagement with the UK Government Interim Chief Construction Adviser (CCA), including an initial analysis of that role’s remit. As a result, the options appraisal will now explicitly consider whether a UK wide or devolved nations approach may better reflect the reality of a single, integrated construction industry.
5. Ongoing engagement with counterparts in the UK Government, and other DAs to understand each administration’s approach to construction regulatory reform and explore alignment, where appropriate.
Planned activity
1. Continue to develop the brief for the procurement of a specialist consultant to undertake an options appraisal.
2. Continue to develop the implementation plan and programme.
3. Continue to engage with the UK Government and other DAs.
Issue 2 - Banning Companies (to stop them being awarded Government contracts)
Reserved area – Yes
Delivery – Reserved matter
Target date – 30/09/2028
Activity since last update
Procurement legislation is a reserved matter. We continue to engage with the UK Government on this issue.
Planned activity
We will continue to monitor what is being done by the UK Government.