Grenfell Tower Inquiry recommendations: progress update - June 2026
The progress update contains information regarding the Grenfell Tower Inquiry recommendations (so far as relevant to Scotland). Information is current up until 1 June 2026.
Theme - Building Standards, fire tests and product certification
Recommendation 5 – Approved Document B Review and Update
Reserved area – No
Delivery – Secondary legislation (Scottish Parliament) & Guidance
Target date – 31/12/2030
Activity since last update
A Scottish Building Regulations: Fire Safety review and Compliance: Call for Evidence (CFE) was opened on 16 January and closed on 10 April 2026.
A total of 57 responses were received. Of these, 51 responses have been published, where respondents granted permission for publication. The published responses are available at: Published responses for Scottish Building Regulations: Fire Safety review and Compliance: Call for Evidence
Procurement activities have been completed, and a contractor has been appointed to undertake the analysis of the CFE responses.
Planned activity
The consultation analysis phase commenced in June 2026, with officials working closely with the appointed contractor to review and analyse the responses received. Subject to the complexity and volume of the responses, the analysis is expected to be completed in Autumn 2026, with publication of the findings following shortly thereafter.
In parallel, officials are progressing arrangements for a Fire Safety Expert Working Group. This includes developing the terms of reference, identifying membership, issuing invitations, preparing the work programme, and seeking the necessary ministerial approvals. The Group will be established to consider both the findings of the Call for Evidence and wider fire safety issues, including matters arising from the Grenfell Tower Inquiry Phase 2 recommendations and the Scottish Government’s response. The Group is expected to be convened and hold its inaugural meeting in mid to late Autumn 2026.
Further information - Scottish Building Regulations: Fire Safety review and Compliance: Call for Evidence - Scottish Government consultations - Citizen Space
Recommendations 6 – 9
- Building Regulations Compliance Warning Implementation
- Stay Put Policy and Evacuation Assessment Review
- Integration of Fire Spread Rate and Inclusive Evacuation Time Assessment Requirements in Building Safety Documentation
- Academic Inclusion in Guidance Advisory Bodies
Reserved area – No
Delivery – Guidance
Target date – 31/12/2030
Update as for Recommendation 5.
Recommendation 10 - Mandatory Fire Safety Strategy Requirements
Reserved area – No
Delivery – Secondary legislation (Scottish Parliament)
Target date – 31/12/2030
Update as for Recommendation 5.
Recommendation 11 - External Wall Testing Methods Development
Reserved area – Yes
Delivery – Reserved matter
Target date – 31/12/2030
Activity since last update
The Scottish Government has liaised with UK Government counterparts regarding ongoing research into testing approaches and methodologies.
Planned activity
The Scottish Government will continue to engage with UK Government counterparts, particularly in relation to reviewing the findings and conclusions of research into testing methodologies. It will also seek representation on any relevant working group established to consider the research outcomes and/or future developments.
Further information – Annual Report February 2026 – The Construction Industry
Progress report May 2026: the construction industry
Recommendation 12 – BS 9414 Usage Guidance Update
Reserved area – No
Delivery – Guidance
Target date – 31/12/2030
Update as for Recommendation 5. Further activity will be considered as part of the expert panel work including engagement with UK Government counterparts (BSR).
Recommendation 13 - Construction Product Certification Reform
Reserved area – Yes
Delivery – Reserved matter
Target date – 30/09/2028
Activity since last update
Construction Product Regulations is a reserved matter and Scotland follows the regime defined for the UK.
A Construction Products Reform Green Paper was published by the UK Government on 25 February 2025 seeking views on proposals for reform by 21 May 2025. Following analysis of the Green Paper responses, a White Paper was published on 25 February 2026 and remained open for views from interested parties until 20 May 2026.
MHCLG is currently analysing feedback on the White Paper consultation and the report will be published in due course.
Planned activity
We will continue to engage with MHCLG on this to hear about next steps when the consultation report is published.
Further information - Construction Products Reform White Paper - GOV.UK.
Recommendation 14 - Test Results Transparency Initiative
Reserved area – Yes
Delivery – Reserved matter
Target date – 30/09/2028
Update as for Recommendation 13.
Recommendation 40 - BS 750 Flow Coefficient Amendment
Reserved area – No
Delivery – Guidance
Target date – 13/11/2026
Activity since last update
The British Standards Institution (BSI) along with an expert panel have prepared a revised draft to amend BS 750 to include a description of the circumstances under which the flow coefficient to which it refers in paragraph 10.2 is to be measured. The draft was issued for public comment on 13 February and closed 13 April 2026. The publication is scheduled for 16 November 2026.
Planned activity
BSD Fire Team to monitor the outcomes of the progress towards the scheduled publication. This will involve monitoring the BSI and UK Government updates.