Waste Reprocessing Infrastructure in Scotland
A report on the waste reprocessing infrastructure in Scotland in accordance with section 23 of the Circular Economy (Scotland) Act 2024.
Appendix 2 – Planning information
Accessed July 2025. Proposed reprocessing facilities that are in planning or have been consented and are under construction.
Site Name: Drumshangie OCCS Greengairs Road EfW and Recycling Plant
Comments: The Drumgray ERC Planning Application was approved by North Lanarkshire Council in August 2020.
300,000 tpa EfW treating non-hazardous residual waste.
200,000 tpa mechanical pre-treatment facility recovering 10,000 tonnes of materials for recycling.
An extension to the existing Incinerator Bottom Ash Pad Area to store and process IBA.
Local Authority: North Lanarkshire
Site Activity (Material / operation): Energy from Waste MRF
Throughput (t/yr): EfW 300,000 MRF 50,000
Current Status: Consented
Site Name: Pond Industrial Estate AD Facility
Comments: 2009 (Feb) Planning Submitted for 200,000 tonne AD facility ref no: 0086/FUL/09.
2011 (March) Planning permission granted.
2023 Bank Renewables look to develop a battery storage 'flexible energy park' in the same location on the Ponds Industrial Estate with no mention of an anaerobic digestion plant.
2024 (Oct) This battery energy storage system is passed through council committee.
Local Authority: West Lothian
Site Activity (Material / Operation): Organics – AD
Throughput (t/yr): 200,000
Current Status: Planning
Site Name: Railway Marshalling Yard, Forres, Moray Anaerobic Digestion Plant
Comments: 2012 (May): Application received by LA 12/00821/SCO.
2012 (June): Status: Unknown. EIA opinion sourced and highlights a number of key issues about the proposed waste facility which require further investigation. Scoping opinion issued.
Local Authority: Moray
Site Activity (Material / Operation): Organics - AD
Throughput (t/yr): 150,000
Current Status: Planning
Site Name: Dunbar Landfill Site Plastics Recycling Facility
Comments: No news since Oct/Nov 2020 - consultation on redrafted plans (smaller no residual washing) - Polymer Recycling Facility
Planning app 20/00001/PAN - pre application request letter May 2020 most recent document. As major development this was required. Nothing more recent to indicate approval. Decision letter issued March but this was to advise proposed consultation activity was acceptable and confirm proposal of application notice required.
No sign of PPC permit application.
20/00005/PAN - Aug-20 submitted proposal of application notice (Status "Decided"). The site was initially proposed by Viridor however the Dunbar landfill site is no-longer owned or operated by Viridor following the sale of its landfill business to Valencia Waste Management in April 2022
Local Authority: East Dunbartonshire
Site Activity (Material / Operation): Plastics
Throughput (t/yr): 100,000
Current Status: Consented
Site Name: Lyon Road Waste Tyre and Rubber Recycling and Processing Plant
Comments: 21/1520/PP - to Scot Gov. 28/08/24 Ministers disagreed with Reporters decision (to refuse) Application Granted planning permission - granted subject to conditions.
Local Authority: Renfrewshire
Site Activity (Material / Operation): Tyre and Rubber
Throughput (t/yr): 100,000
Current Status: Planning
Site Name: Lochaber Smelter - Aluminium Recycling Facility
Comments: 22/09/2021 Plans approved by Cllrs & planning permission granted - Alvance Aluminium. Article on their website - Plan to break ground in 24/25 - bringing materials to market in 26/27.
Local Authority: Highland
Site Activity (Material / Operation): Aluminium
Throughput (t/yr): 100,000
Current Status: Planning
Site Name: Swinhill Anaerobic Digestion (Biomethane) Plant
Comments: 2023 (June): Application Received P/23/0733. South Lanarkshire council considers proposal does not require an EIA.
Local Authority: South Lanarkshire
Site Activity (Material / Operation): Organics – AD
Throughput (t/yr): 65,000
Current Status: Planning
Site Name: Longman Landfill Site Waste Material Recovery Facility
Comments: Transfer station was completed in 2023, no dirty MRF
19/00503/FUL - application permitted. MRF to process BMW, office, welfare etc. Publicity that it’s a transfer station, no MRF - materials to Dunbar EFW.
Local Authority: Highland
Site Activity (Material / Operation): MRF (for reuse)
Throughput (t/yr): 65,000
Current Status: Constructing
Site Name: Claylands Road AD Facility
Comments: 2016 (May) Application granted permission with conditions to Muirhall Energy Ltd (Newbridge Biogas Ltd) 10/02552/FUL. Company looking to develop the site have lots of projects active at the moment however almost all focus on wind turbines.
Local Authority: City of Edinburgh
Site Activity (t/yr): 40,000
Current Status: Consented
Site Name: Auldhill Drive, Bridgend Recycling Facility
Comments: Planning submitted 0542/FUL/19 - Use of land as a recycling facility for inert materials up to 24.500 tonnes (partly in retrospect). Consented 2019.
Local Authority: West Lothian
Site Activity (Material / Operation): Not specified
Throughput (t/yr): 24,500
Current Status: Consented
Site Name: Dalmagarry Quarry - Inert Construction and Demolition Waste Recycling Facility
Comments: 22/02166/FUL - planning application still under consideration. NO update / decision provided. Materials demolition/ construction – sand
Local Authority: Highland
Site Activity (Material / Operation): Construction & Demolition
Throughput (t/yr): 20,000
Current Status: Planning
Site Name: Swinlees Quarry Inert Construction Materials Recycling Plant
Comments: 22/00699/PP - recycling inert construction using mobile plant and relocation of concrete plant operations. Approved subject to conditions 30/03/23
Local Authority: North Ayrshire
Site Activity (Material / Operations): Construction & Demolition
Throughput (t/yr): 20,000
Current Status: Planning
Site Name: Ravelaw Farm AD Plant
Comments: This site has multiple applications for anaerobic digestion plants from March 2014 (14/00763/FUL), July 2014 (14/00763/FUL) and July 2015 (15/00792/FUL).
The first application was 'Withdrawn', second application in Jul 2014 has a status of 'Decided'.
The second, July 2014 proposal planned to be a small scale AD plant with all feed material being sourced / grown on the farm. This will not include municipal waste. 8th Dec 2014: Councillors refused permission. Planning officials had recommended approval. The third application was approved Oct 2015 and stated work had to commence within 3 years. Photos logged showing that work commenced on site in Oct 2018 however letters show disagreement between council and site as to whether it justifies as 'commencement of work or not'. Undetermined whether build continued.
Local Authority: Scottish Borders
Site Activity (Material / Operations): Organics – AD
Throughput (t/yr): 7,000
Current Status: Planning
Site Name: Longmorn Anaerobic Digestion Plant (Acorn Bioenergy Ltd)
Comments: Application 23/00709/APP . Received 1st May 2023, revised December 2024. Proposal to take distillery waste from four local distilleries (80% of feedstock from distillery co-products including pot ale, syrup and draff) and local farmers (break crops)
Local Authority: Moray
Site Activity (Material / Operations): Organics – AD
Throughput (t/yr): unknown
Current Status: Planning