Planning and Environmental Appeals Division: annual review 2024 to 2025

Planning and Environmental Appeals Division's (DPEA) annual review of its performance for 2024 to 2025.


Appendix A

Statistics On Workload And Performance Against Targets

Table 1: Volume Of Cases* Handled By DPEA
Business year In hand at start of the year Received Delegated appeals decided Reports submitted Withdrawn In hand at end of the year
2024 to 2025 202 1002 911 46 37 210
2023 to 2024 212 613 498 69 57 201
2022 to 2023 209 625 502 58 62 212
2021 to 2022 199 577 468 53 46 209
2020 to 2021 191 438 365 37 28 199

*Includes appeal and non-appeal cases

The total number of cases sisted/suspended as of 31 March 2025 was 54.

Table 2: Types Of Cases Received
Type Of Case 2020 2021 2021 2022 2022 2023 2023 2024 2024 2025
Certificate of Lawful Use & Development Appeal 0 1 5 39 415
Planning permission appeals 229 258 245 230 226
Planning enforcement appeals 37 76 82 109 171
Conservation area consent, listed building consent and listed building enforcement appeals 48 51 56 65 55
Advertisement consent, discontinuance notice and advertisement enforcement appeals 33 23 43 39 38
High Hedge appeal 8 20 16 18 9
All other types of appeal 46 65 56 49 53
Subtotal: all types of appeals 401 494 503 549 967
Called-in application 1 3 1 0 0
Compulsory Purchase Order 5 5 3 9 2
Core Paths Plan 1 1 0 0 0
Discontinuance Order 0 0 0 0 1
Flood Prevention Scheme 0 1 0 1 1
Listed Building Notified Application 1 0 0 1 0
Local Development Plan 4 3 4 0 0
Notification Direction 0 0 1 1 2
Notified application 6 8 13 10 3
Power Station 0 0 0 1 0
Public path creation/diversion/extinguishment order 0 1 0 0 1
Purchase Notice 0 0 0 2 0
Revocation order 0 1 0 1 1
Roads order 2 0 2 0 0
Section 36 Wind Farm 8 5 9 3 10
Section 37 Transmission line 0 5 1 0 0
Stopping up order 1 5 1 2 2
Strategic Development Plan 0 0 0 0 0
Traffic Regulation Order 0 1 2 5 0
Wayleave 8 44 85 28 12
Called-in application 1 3 1 0 0
Subtotal: all types of non-appeal cases 37 83 122 64 35
All Cases Received 438 577 625 613 1002
Table 3: Breakdown Of Cases Received By Their Characteristics
Characteristics 2019 2020 2020 2021 2022 2023 2023 2024 2024 2025
Advertisement 33 24 46 41 38
Agricultural 9 7 12 6 11
Animal (cattery, kennel, stable etc.) 3 4 4 4 1
Battery Storage 0 0 0 0 9
Building Alterations (householder) 72 72 64 71 64
Building Alterations (non-householder) 12 20 17 24 23
Business 22 9 23 10 12
Car park 12 17 17 12 11
Caravan and Campsites 4 13 16 17 53
Cemetery/Religious Building 1 1 3 2 2
Chimney/Flue 1 0 0 0 2
Community Asset Transfer 3 4 4 1 1
Compulsory Purchase Order 4 5 3 8 2
Demolition 13 13 23 19 17
Designation of Building/Monument 2 6 2 2 5
Development Plan (Local) 4 3 5 1 0
Dock/Harbour 1 1 0 0 1
Environmental Appeal 4 7 7 12 213
Fencing/Wall 20 31 16 16 20
Fish Farm 1 5 2 0 212
Flood Prevention Scheme 0 1 0 1 2
Gatecheck 0 0 0 0 12
Hazardous Substance 0 0 0 0 0
Hedge 8 20 15 18 9
Holiday/Leisure 10 22 8 8 48
Hospital/Medical Centre 2 1 0 0 0
Hot Food Takeaway 5 9 4 3 7
Hotels 20 23 1 2 7
House in Multiple Occupation 1 4 5 6 1
Housing (10 or more houses) 47 55 38 26 25
Housing (more than one house) 21 22 24 28 17
Housing (single dwelling) 47 43 65 40 33
Hydro/Solar Power 1 0 1 4 2
Industrial 1 4 3 1 3
Landscaping 15 37 38 15 34
Leisure Facility/Ground 7 10 7 8 6
Meteorological/Anemometrical Mast 0 1 0 0 0
Mineral Extraction 3 3 3 0 2
Nursing/Care/Retirement Home 3 3 4 0 0
Other 4 21 13 27 8
Path 5 8 1 7 9
Petrol Station 0 1 1 0 0
Power Station/Energy from Waste 0 2 4 2 1
Recycling 0 1 0 0 0
Restaurant/Cafe/Licensed Premises 13 9 12 8 9
Retail (food) 13 6 2 2 5
Retail (non-food) 9 2 7 5 1
Road/Bridge 14 9 12 13 8
Scheduled Monument 0 1 1 0 0
School/Educational 4 2 5 3 1
Shed/Garage 24 27 13 11 11
Short stay accommodation 0 9 58 156 552
Storage (non-warehousing) 12 11 7 10 9
Student Accommodation 8 1 4 8 10
Substation/Transmission Line/Pipeline 0 6 1 0 0
Telecommunication 15 13 12 8 18
Traffic Regulation Order 1 1 2 2 0
Transport 0 1 2 0 2
Travelling Persons Site 1 2 0 0 0
Tree 4 22 11 8 8
Warehouse/Distribution 0 3 3 1 2
Waste Disposal 0 0 1 4 1
Water/Sewage 8 8 10 35 25
Wayleave 8 44 84 28 10
Wind Farm (two or more turbines) 23 24 16 10 16
Wind turbine (single) 3 0 0 0 2
Windows - Timber 1 7 4 6 7
Windows - UPVC 6 12 15 13 11
Table 4a: Appeal Cases Success Rates By Method Of Determination
Delegate appeals Number decided Considered by oral process Considered by site visit/review of written submissions All cases allowed
Total Allowed Percentage Total Allowed Percentage Allowed Percentage
Planning permission 152 1 1 100% 151 74 49% 75 49%
Planning enforcement 111 0 0 0% 111 31 28% 31 28%
Conservation area consent, listed building consent and listed building enforcement 55 0 0 0% 55 16 29% 16 29%
Advertisement consent, discontinuance notice and advertisement enforcement 31 0 0 0% 31 16 52% 16 52%
High Hedge appeal 13 0 0 0% 13 10 77% 10 77%
All others 423 1 0 0% 422 37 9% 37 9%
All Delegated Appeals 785 2 1 50% 783 184 23% 185 24%
Non-delegated Appeals 2 2 0 0% 0 0 0% 0 0%
All Appeals 787 4 1 25% 783 184 23% 185 24%

*In addition, a further 126 appeals were turned away as we had no powers to determine them

Table 4b: Non-Appeal Cases Success Rates by Method Of Determination
Case types Number decided Considered by oral process Considered by site visit/review of written submissions All cases allowed
Total Allowed Percentage Total Allowed Percentage Allowed Percentage
Called-in application 1 1 1 100% 0 0 0% 1 100%
Compulsory Purchase Order 4 4 4 100% 0 0 0% 4 100%
Notification Direction 1 0 0 0% 1 1 100% 1 100%
Notified application 11 2 2 100% 9 5 56% 7 64%
Power Station 1 1 1 100% 0 0 0% 1 100%
Section 36 Wind Farm 5 5 4 80% 0 0 0% 4 80%
Section 37 Transmission line 6 6 6 100% 0 0 0% 6 100%
Stopping up order 4 2 2 100% 2 2 100% 4 100%
Wayleave 5 3 3 100% 2 2 100% 5 100%
Total: All Non-appeal Cases 38 24 23 96% 14 10 71% 33 87%
Table 5: Success Rates for Delegated Appeals by Planning Authority
Planning authority Appeals decided Appeals allowed Success rate
Aberdeen City Council 14 7 50%
Aberdeenshire Council 12 7 58%
Angus Council 6 1 17%
Argyll and Bute Council 9 3 33%
Cairngorms National Park Authority 2 0 0%
City of Edinburgh Council 336 61 18%
Clackmannanshire Council 3 3 100%
Comhairle nan Eilean Siar (Western Isles Council) 2 0 0%
Dumfries and Galloway Council 8 5 63%
Dundee City Council 7 3 43%
East Ayrshire Council 3 0 0%
East Dunbartonshire Council 3 3 100%
East Lothian Council 45 6 13%
East Renfrewshire Council 3 1 33%
Falkirk Council 5 2 40%
Fife Council 13 6 46%
Glasgow City Council 182 22 12%
Highland Council 15 10 67%
Historic Environment Scotland 1 0 0%
Inverclyde Council 1 1 100%
Loch Lomond and the Trossachs National Park Authority 1 1 100%
Midlothian Council 3 2 67%
Moray Council 1 1 100%
North Lanarkshire Council 5 1 20%
Orkney Islands Council 7 1 14%
Perth and Kinross Council 32 19 59%
Renfrewshire Council 2 0 0%
Scottish Borders Council 11 5 45%
Scottish Forestry 1 1 100%
South Ayrshire Council 5 1 20%
Planning authority Appeals decided Appeals allowed Success rate
South Lanarkshire Council 12 3 25%
Stirling Council 11 2 18%
West Dunbartonshire Council 1 0 0%
West Lothian Council 23 7 30%
Total 785 185 24%

Note: if an authority is not listed in table 5 it means no delegated decisions have been issued for sites within said authority’s area within the period.

Table 6a: Gatecheck Examinations Completed
Gatecheck Examination Number of reporters Weeks to complete
Glasgow City Council City Development Plan 2 - Evidence Report Gate Check - Re-Submission 1 5.2
Dumfries And Galloway Council Local Development Plan 3 - Evidence Report Gate Check. 1 10.5
East Lothian Council Local Development Plan 2 - Evidence Report For Gatecheck 1 12
Falkirk Local Development Plan 3 (Ldp3) - Evidence Report Submission For Gate Check 1 12
East Lothian Council Local Development Plan 2 - Evidence Report For Gatecheck 1 3.1
East Renfrewshire Local Development Plan 3 - Evidence Report Gate Check 1 12.1
Midlothian Council Local Development Plan 2 - Evidence Report Gate Check 1 11.6
Glasgow City Council City Development Plan 2 - Evidence Report Gate Check 1 12
Moray Council Local Development Plan 2027 - Evidence Report Gate Check 1 13.5
Fife Council Local Development Plan 2 - Evidence Report Gate Check 1 11
Table 6b: Gatecheck Examinations in Hand or Completed After End Of March
Gatecheck Examination Received
Stirling Local Development Plan 3 - Evidence Report For Gate Check Examination 28/03/2025
Perth And Kinross Local Development Plan 3 – Evidence Report – Gate Check Request 27/03/2025
Table 7: Performance Against Our Targets
Procedure Target number of weeks to determine Number of appeals Performance against target Average weeks taken to determine
Written Submissions 12 688 93.06% 11.6
Further Written Submission 20 96 72.92% 23.3
Hearing 40 2 50% 41.1
Inquiry 50 0 n/a n/a
Table 8: Time Taken to Submit Reports
Case types Reports submitted Average weeks taken to submit
Recalled Planning/Listed Building Appeals 3 29.5
Called-in & Notified Applications 10 30.7
Compulsory Purchase Orders 7 36.3
Other Orders 9 25.3
Section 36 Wind Farm Applications 8 57.9
Wayleave Applications 9 25.5
Table 9 Planning Authorities’ Performance In Their Submission Of Completed PARFS
Planning authority PARFs received in year Returned within 21 days % Returned within 21 days Average days to submit
Aberdeen City Council 12 9 75% 22.0
Aberdeenshire Council 11 7 64% 23.7
Angus Council 5 3 60% 17.8
Argyll and Bute Council 10 6 60% 28.5
Cairngorms National Park Authority 1 0 0% 28.0
City of Edinburgh Council 344 285 83% 16.2
Comhairle nan Eilean Siar (Western Isles Council) 3 3 100% 17.7
Dumfries and Galloway Council 5 1 20% 28.2
Dundee City Council 9 7 78% 16.9
East Ayrshire Council 4 2 50% 22.3
East Dunbartonshire Council 3 0 0% 26.3
East Lothian Council 39 36 92% 11.2
East Renfrewshire Council 5 2 40% 27.6
Falkirk Council 5 3 60% 20.2
Fife Council 13 8 62% 24.2
Glasgow City Council 177 104 59% 23.6
Highland Council 25 14 56% 21.5
Historic Environment Scotland 2 2 100% 21.0
Inverclyde Council 4 3 75% 21.0
Loch Lomond and the Trossachs National Park Authority 2 0 0% 30.5
Midlothian Council 4 4 100% 19.5
Moray Council 3 0 0% 34.7
North Ayrshire Council 1 0 0% 25.0
North Lanarkshire Council 6 0 0% 25.7
Orkney Islands Council 9 6 67% 22.3
Perth and Kinross Council 25 19 76% 18.0
Planning authority PARFS received in year Returned within 21 days % Returned within 21 days Average days to submit
Renfrewshire Council 5 5 100% 18.0
Scottish Borders Council 9 5 56% 24.2
Stirling Council 6 4 67% 20.0
West Dunbartonshire Council 1 1 100% 21.0
Overall 786 562 72% 22.8