Water - Investment Planning and Prioritisation Group (IPPG) report: quarter 3 -2022 to 2023
Sets out how Scottish Water is progressing in developing interventions to address the needs on the ‘Development List’ up to the end of December 2022 (quarter 3 2022 to 2023).
Appendix A: Inflation Assumption
The revised inflation assumption used are shown in Table 1. We recognise that some costs within our capital programme are increasing at a greater rate than the current CPI projection. We continue to assess and monitor this Capital Price Inflation value to allow us to better understand potential cost increases across the programme.
| Inflation Assumption | 2021-22 | 2022-23 | 2023-24 | 2024-25 | 2025-26 | 2026-27 |
|---|---|---|---|---|---|---|
| Programme Inflation Assumption | 4.0% | 10.0% | 6.9% | 1.9% | 0.9% | 2.0% |