Infrastructure Investment Plan 2021-22 to 2025-26: major capital projects progress update - August 2025
Information relating to projects with a capital value of £5 million or more which are at the outline business case (or equivalent) approved stage or beyond.
Sector: Further Education
Project: Dunfermline Learning Campus (College element)
Business case approved stages: New build college campus in Dunfermline, Fife. Following Scottish Government approval to award the contract in December 2022, the cost of the project was estimated at £131 million with project completion estimated for December 2024 and an operational start date of spring 2025.
Progress at February 2025: The cost of the project remains unchanged since last reported at £154.5 million. The construction phase of the project is on track to be completed by September 2025, with the campus due to be fully operational by January/February 2026.
Progress at August 2025: No change in cost or construction completion date since the last report. The campus will be fully operational by January/February 2026 and open to students in autumn 2025.
Contact for public enquiries: email: ameldrum@sfc.ac.uk