Building regulations - fire safety and compliance call for evidence: analysis of responses

This analysis of consultation responses will help inform Scottish Government policy decisions in response to the Grenfell Tower Inquiry Phase 2 recommendations, including wider changes to Scottish Building Standards, fire safety regulations and guidance, and the compliance plan approach.


11. CPA: Pre-warrant stage

In the CPA for HRBs, a formal pre-application or pre-warrant stage is included, which must be completed prior to building warrant applications. The purpose of this is for pre-warrant discussions to focus on compliance, and management and mitigation of non-compliance risks during the construction phase. Following stakeholder discussions, a proposal has been made for the pre-warrant process to begin with an application for a Compliance Plan in Principle, submitted a minimum of 12 weeks prior to the first submission of a building warrant to the project. That process, which ends with a Compliance Plan in Principle being issued by the verifier, must be completed prior to a verifier legally registering an application for the building warrant. This period of 12 weeks mirrors the requirements for the Planning Application Notice for Major Developments being submitted prior to submitting a planning application.

Q14a. Do you agree with the proposed minimum 12-week timescale for submission to a verifier of an Application for Compliance Plan in Principle for a High Risk Building? Please provide any evidence or examples to support views, contribution or comments.

Respondent type Sample size (n=) % Yes % No % Not sure % No answer
All respondents 57 39 9 16 37
All answering 36 61 14 25 -
Individuals 6 83 0 17 -
Organisations: 30 57 17 27 -
- Trade Association 5 80 20 0 -
- Local Authority 7 57 29 14 -
- Professional Body 4 25 25 50 -
- Consultancy 4 50 25 25 -
- Construction Industry 2 100 0 0 -
- Manufacturer 2 50 0 50 -
- Housing Provider / RSL 2 50 0 50 -
- Other 4 50 0 50 -

Among those answering Q14a, three fifths (61%) agreed with the proposed minimum 12-week timescale for submission to a verifier of an Application for Compliance Plan in Principle for a HRB, while 14% disagreed and 25% were unsure. While 83% of individuals were in favour, support was lower among organisations at 57%. Views varied by type of organisation, ranging from 100% of the construction industry and 80% of trade associations that answered in favour, to 25% of professional bodies.

Three quarters of all respondents commented on Q14a. The most mentioned themes, from most to least prevalent, were general agreement with the proposed timescale, concerns and considerations for implementation, and issues with the proposed 12-week timescale.

Yes, time needed for the process and addressing issues early

Several respondents expressed general agreement with the proposed minimum 12-week timescale for submission to a verifier of an Application for Compliance Plan in Principle for a HRB. Respondents thought the proposed 12-week minimum l was proportionate, appropriate, reasonable and achievable for HRBs.

Some respondents noted that a 12-week minimum would help to address any issues early and prevent challenges later in the process. In particular, it was thought to encourage realistic, proper planning at the project outset, including ensuring that the design is competent, complete, and with sufficient detail. This minimum timeframe was also thought to support early identification of non-compliance and risks prior to the construction process, improving overall building construction and compliance, and reducing the need for remedial work. The early identification of these risks by verifiers through this process was also specifically mentioned.

“High Risk Buildings present increased and foreseeable risks to life safety, and early, structured engagement on compliance is essential to prevent design decisions that are difficult or costly to correct once construction is underway. A defined pre-warrant period encourages proper planning, competent design input, and early identification of compliance risks…Any additional time required at the pre-warrant stage is justified by the reduction in downstream non-compliance, remedial work and enforcement action, which ultimately improves safety outcomes and reduces overall project risk.” - Individual

A minimum of 12 weeks was suggested to sufficiently allow time for applications and processing of applications by some respondents. In particular, it was thought to allow sufficient time for verifiers to process applications. This includes having conversations, familiarising themselves, determining information requirements, warrant interrogation, ensuring plans meet compliance, scrutinising plans, and identifying any issues or concerns. One respondent also highlighted that the 12-week timeframe allows for Compliance Plans to be prepared for submission prior to seeking verifier approval.

“We agree with the proposed minimum 12-week timescale as this provides sufficient time for the applicant, design team, and verifier to engage meaningfully on compliance issues.” - ROCKWOOL Ltd

A small number of respondents highlighted that the 12-week minimum would help to support consistency in approaches across the industry:

  • Two respondents highlighted that it aligned with the Planning Application Notice timeframe for Major Developments prior to submitting a planning application, supporting synergy in timelines across relevant parties.
  • The 12-week minimum aligns with requirements in Wales and England.
  • Findings from the English BSR/Golden Thread approach were referenced, where a period of 12 weeks was seen as fair, noting that some Gateway approvals are taking longer than that period. Learnings from Gateway could assist, such as highlighting the need for improved engagement, support systems, and pre-consultation.
  • The minimum time required for verifiers to review testing data to determine building safety using mass timber or Modern Methods of Construction was thought to be 12 weeks.

“Aligning the timescale with the Planning Application Notice period for Major Developments provides consistency across regulatory processes and gives clarity and predictability to applicants, verifiers and stakeholders.” - Individual

No, issues with the timeline and suggestions

Issues with the 12-week timeline were raised by some respondents, notably that in some instances it could cause delays or be unachievable. Concerns included:

  • Delays caused by the 12-week minimum for projects that have multiple revisions, unachievable timescales for HRB funding and timescales, and cladding remediation could introduce additional time, risks and costs.
  • The level of detail required may not be available, or there may be changes throughout the 12 weeks.
  • Too early engagement could be less meaningful if relevant details, design, and the construction team are not yet confirmed.
  • That the length of time is dependent on the knowledge of the verifier.
  • That planning can be subjective as opposed to technical, which is required for the CP; therefore, a 12-week review at that stage may be excessive.

To address concerns of timescale, one respondent suggested piloting the 12-week minimum to see whether it would work in practice, prior to becoming mandatory.

“In the case of cladding remediation, not only does this extend the length of time the building has potentially dangerous cladding, it also potentially extends the length of time costly interim measures.” - Scottish Federation of Housing Associations

“There are often many changes throughout these 12 weeks prior to submission period. This proposal above could then de-value the first pre-warrant meeting, causing abortive work. Also, many applications are not at the required design stage 12 weeks prior to submission, for the pre-warrant to have a significant value. This change in approach to 12 weeks would take a lot of change in industry. Although this 12-week period could be a industry best practice, it should not be mandated, given the negatives outweigh the positives.” - Dundee City Council Building Standards

Some respondents disagreed or were not sure about the proposal and made suggestions. A few commented on the need for the approach to be realistic and proportionate to project scale, nature, type, complexity, urgency and capacity of verifiers. Suggestions included:

  • Having transparent guidance for each stage in relation to information requirements.
  • Implementing a pre-site-start 12-week requirement instead.
  • Instead of a minimum scale, provide a maximum to provide greater clarity on timescales.
  • Having conversations on submission of the building warrant in relation to compliance prior to the granting of the warrant. The same respondent suggested having pre-application conversations determined in terms of timescales by specific applicants rather than legislative timescales.

“It was also suggested by some members that instead of having a 12-week pre-warrant requirement, the process could shift to a 12-week pre-site-start requirement. This way, the warrant application could be submitted, and the information for the compliance plan could be developed in parallel. The requirement would be to submit the compliance plan in principle information 12 weeks before the official site start, with sign-off completed before work begins on site.” - Scottish Federation of Housing Associations

Implementation considerations and need for more information

Several respondents detailed concerns and considerations for implementing this proposed 12-week minimum timescale. Calls for adequate resourcing if this proposal goes ahead were highlighted. Existing capacity and resourcing constraints in teams were highlighted, such as having sufficient staff with required skills to process applications, which could be exacerbated without additional resourcing. Requests for guaranteed response times for decisions on CP applications were made to prevent adding complexity or delays to projects. Other singular comments for consideration include:

  • Including content requirements for the CP in Principle application, e.g. preliminary identification of SCEs in the performance standards to support verifier assessments, and a preliminary strategy document on fire safety.
  • Ensuring verifiers know about the condition of void networks.
  • Ensuring verifiers are paid appropriately for pre-warrant work.
  • Recognising the Grenfell Phase 2 Inquiry report’s evidence in relation to the need for compliance scrutiny to occur prior to construction.
  • Considering further the participation of SFRS in the pre-warrant stage.
  • Having engagement between applicants and verifiers prior to the 12 weeks.

“…the CPA in Principle application for an HRB must include a preliminary SCE identification — a list of the Safety Critical Elements applicable to the building type, with their proposed Performance Standards and the compliance route to be used for each. This forces the design team to identify at the pre-warrant stage what the building's fire safety depends on and allows the verifier to assess whether the proposed compliance route for each SCE is appropriate for the building type, use, and construction method.” - Organisation

Some respondents called for more information and clarification on this proposal. A range of singular comments were made, including:

  • How the process will work when staged building warrants are used, noting this is often done for larger projects to reduce programmes and enable site starts to begin earlier. The respondent noted that usually for Stage 1 warrants substructures are submitted, while superstructure packages are still in development. They commented that not all details were thought to be required as part of the CP when substructure warrants are ready to be submitted or 12 weeks in advance. This was raised with a concern that it could lengthen processes for these projects.
  • How the 12-week period is defined, how it relates to the scope of design work for fire safety, and what it must contain.
  • How the proposal will fit with the Royal Institute of British Architects (RIBA) stages, noting the need to not complicate a cladding or façade review.
  • How realistic a 12-week period is in practice, noting dependence on the relevant knowledge of verifiers.
  • How much detail will be required in submissions, with a respondent noting that some parts of the design for fire safety could be addressed in RIBA stages 3 and 4. They also suggested having a discussion pre-warrant with approvers and having a consistent pro-forma template for all HRBs.

“Based upon our experience, we would question whether a minimum 12-week period would be realistic. Completion to this timescale would depend on the level of knowledge the verifier has of the project at the time of the submission and recommend the following aspects are considered: Who is the verifier and what are their relevant competencies for the construction type; Will the verifier be involved throughout the design process to have an awareness of the proposed design; At what stage is the compliance plan in principle expected; and Will the verifier be involved in multiple stages of the construction or is the expectation they will only verify at project completion.” - Arup

Q14b. Do you agree that a verifier should only register a building warrant for a High Risk Building after a Compliance Plan in Principle has been issued? Please provide any evidence or examples to support views, contribution or comments.

Respondent type Sample size (n=) % Yes % No % Not sure % No answer
All respondents 57 49 5 7 39
All answering 35 80 9 11 -
Individuals 6 83 0 17 -
Organisations: 29 79 10 10 -
- Trade Association 5 60 20 20 -
- Local Authority 7 71 14 14 -
- Professional Body 4 75 25 0 -
- Consultancy 3 67 0 33 -
- Construction Industry 2 100 0 0 -
- Manufacturer 2 100 0 0 -
- Housing Provider / RSL 2 100 0 0 -
- Other 4 100 0 0 -

Four fifths (80%) of those answering agreed a verifier should only register a building warrant for a HRB after a Compliance Plan in Principle has been issued. In contrast, 9% disagreed, and 11% were unsure. Four fifths of both individuals (83%) and organisations (79%) agreed with this approach, as did at least 60% of each type of organisation.

Just over three quarters of all respondents commented on Q14b. The most mentioned themes were agreement with the proposal and considerations for implementation.

Yes, address issues early and supports robust processes

The most prevalent theme, mentioned by several respondents, was agreement with the proposal for verifiers only to register building warrants for HRBs after a Compliance Plan in Principle has been issued. This approach was felt to be important in terms of sequencing of the CPA, and reasonable given Scottish building warrants represent Stage 4 RIBA designs that are fully developed. Another respondent thought it was sensible, as they felt it would strengthen the Scottish HRB regulatory framework.

“Yes — without qualification. The sequencing of CPA in Principle before building warrant registration is the single most structurally important procedural change in the entire Compliance Plan Approach, and the evidence for making it mandatory without exceptions is direct and unambiguous.” – Organisation

“Overall, the requirement for a Compliance Plan in Principle to be issued prior to a building warrant registration is a sensible control measure that should strengthen the regulatory framework for high risk buildings in Scotland.” - FETA

Some respondents supported the proposal as they believed it would help to identify and address compliance issues early, supporting safe and quality designs from the outset. It was also thought to reduce issues later, support ease of application access, and enable clear compliance plans for construction. Other points related to this theme included:

  • Verifier resources will be used more efficiently, as they will only process pre-vetted, high-quality applications. In turn, it would also decrease amendments to warrants.
  • Support for early consultation on designs with relevant professionals and CPM.
  • Reduced risks to approvals, through verifier discussions taking place prior to construction, meaning reduced risk designs.
  • Alignment with the regulatory framework relating to prioritisation of life safety, e.g., supporting assurance of regulatory oversight and safety measures in place from the start, which is of particular importance for HRBs.

“This helps ensure that major compliance risks are addressed at an early stage, encouraging higher quality and easier to assess applications” - ROCKWOOL Ltd

The proposal was thought by some respondents to strengthen robust processes as part of the CPA. They emphasised that this process would support improved sequencing, efficiency, safety, expectation clarity, coordination, verifier confidence and accountability. It was also felt able to reduce later challenges and disputes and prevent warrant attrition. By addressing necessary checks upfront, it was also thought to support an overall increase in compliance in a smoother manner and support efficient planning and delivery by contractors. For instance, one respondent highlighted that this proposal was necessary as part of the CPA, and supported process transparency, with clarity in the audit trail and risks identified upfront, preventatively.

No, alternative suggestions and concerns

Alternative suggestions were made by some respondents who disagreed or were unsure of the proposal in the closed question. Calls were made for a more flexible approach and to work on a case-by-case basis, considering submission quality, team and verifier competency, and complexity. Respondents also made suggestions on when the CP should occur. One respondent suggested the CP should happen prior to the warrant process being underway, and another suggested to approve warrants on condition of a CP agreement and CPM appointment prior to construction on site beginning.

“Each case should be taken on its own merits, taking into consideration the quality of submission, the complexity, the competence of the design team and verifier, etc. An example: if an application for an HRB is submitted, and it is of a quality standard, with a certificate of design for both structure and energy, a fire engineered solution presented with alternative to guidance clearly justified, etc; what benefit would there be to the project holistically, in rejecting this submission to ask for a pre-warrant and CP in principle NOTE: they would have a compliance plan requirement through the building warrant anyway.” - Dundee City Council Building Standards

Two respondents detailed concerns with the proposed approach, notably that pre-warrants may not lead to quality submissions and that the approach did not align to existing construction and design processes.

Considerations for implementation

Several respondents proposed considerations for the implementation of this proposal. Of these suggestions, most mentioned was the need for clear, defined timescales on decisions from verifiers to prevent delays and increase costs. Other comments included:

  • Providing clarity on what good outcomes and engagement look like.
  • Having well-resourced verifiers to engage prior to application submission and determine minimum requirements for content.
  • Introducing sequencing exceptions, where delays or increased costs to construction could occur.
  • That the proposal should not impact phased building warrant applications.
  • Giving detailed, clear guidance on what will happen to building warrant applications already in the pipeline should this proposal come into effect.
  • Clarity on how the approvals and consultations on the Compliance Plan and building warrants will run in relation to each other, with a suggestion for these to occur at the same time.
  • Greater guidance on the CP in principle project stage, and legislation on expectations for the building warrant and CP in principle during design.

“…should not interfere with phased building warrant applications. Industry feedback emphasises that the concept supports coordinating essential checks (fire alarms, cavity barriers, operations verification) upfront, but the process must align with existing staged warranting practice rather than creating a single pre-commencement blockage.” – SPF