Scotland’s Cladding Remediation Programme monthly management information: September 2025
This report presents management information for Scotland’s Cladding Remediation Programme to provide an indication of progress on a monthly basis.
Part of
Single Building Assessments
As at 30 September 2025, the Cladding Remediation Programme had been informed that 16 Single Building Assessments (SBAs), based on the specification published in June 2024, had been completed. This includes the high-priority SBAs that the Scottish Government commissioned for buildings that were identified as part of the pilot programme.
All 16 completed SBAs identified that remedial work was required.
As at 30 September 2025, the Scottish Government Cladding Remediation Programme were not aware of any other SBAs that were yet underway but had not been completed.