19. The most recent figures indicate that 17 SBAs have been completed. These comprise:
- the 13 SBAs that were directly commissioned and funded by the Scottish Government
- three SBAs that were commissioned by Registered Social Landlords and funded by Scottish Government
- one SBA that has been funded by a developer.
20. A further 29 SBA reports received by the Scottish Government have not been carried out in full accordance with the published specification or were submitted in advance of being fully completed. We are working with the commissioning parties to ensure that the SBAs concerned are updated as required.