Planning Performance Statistics 2020/21: Quarterly (October 2020 To March 2021)
This report presents summary statistics on planning application decision-making timescales for October 2020 to March 2021, as well as historic data back to 2016/17. It is based on data collected from Local and Planning Authorities as part of the Planning Performance Framework (introduced in 2012).
This document is part of a collection
10. Legacy Cases
One legacy case was decided in quarter three. The decided application was subject to a processing agreement. Two legacy cases were decided in quarter four, one with and one without a processing agreement.
Tables 4 to 9 show the legacy cases decided in the final six months of 2020/21 by planning authority and development type.
Quarter 3 2020/21 - Decided legacy applications with processing agreements
Local Authority | Number of Legacy Cases | % meeting agreed timescales |
---|---|---|
East Lothian | 1 | 100% |
Total | 1 | 100% |
Development Type | Number of Legacy Cases | % meeting agreed timescales |
---|---|---|
Listed Building Consent | 1 | 100% |
Total | 1 | 100% |
Quarter 4 2020/21 - Decided legacy applications without processing agreements
Local Authority | Number of Legacy Cases | Average Decision Time (weeks) |
---|---|---|
West Dunbartonshire | 1 | 939.0 |
Total | 1 | 939.0 |
Development Type | Number of Legacy Cases | Average Decision Time (weeks) |
---|---|---|
Minerals - Local with EIA | 1 | 939.0 |
Total | 1 | 939.0 |
Quarter 4 2020/21 - Decided legacy applications with processing agreements
Local Authority | Number of Legacy Cases | % meeting agreed timescales |
---|---|---|
East Ayrshire | 1 | 0% |
Total | 1 | 0% |
Development Type | Number of Legacy Cases | % meeting agreed timescales |
---|---|---|
Housing - Major | 1 | 0% |
Total | 1 | 0% |