| Capital (£m) | ABR position | Changes at SBR | SBR position | Changes since SBR | Latest position |
|---|---|---|---|---|---|
| Barnett Funding | 6,255.3 | 0.7 | 6,256.0 | 36.0 | 6,291.9 |
| Capital Borrowing | 471.7 | (42.0) | 429.7 | 0.0 | 429.7 |
| Scotland Reserve | 31.0 | 4.0 | 35 | 0.0 | 35 |
| ScotWind | 341.0 | (188.0) | 153.0 | 0.0 | 153.0 |
| City Deals | 122.0 | (47.8) | 74.2 | 0.0 | 74.2 |
| Other | 9.0 | 37.8 | 46.8 | 2.0 | 48.8 |
| Total Capital Funding | 7,230.0 | (235.3) | 6,994.8 | 38.0 | 7,032.7 |
| Total Capital Budget allocated | 7,229.7 | (258.3) | 6,971.2 | 0.0 | 6,971.2 |