Information requested
I understand that the Scottish Government received approximately £97.1 million during the 2021/22 financial year.
1. How much has been spent to date ?
2. Which projects was the money spent on ? ( Breakdown per project with supporting documentation )
3. What is the remaining balance of the funding received ?
4. What is the future planning for the balance and timeline for implementation ?
5. Where is the money located , and what annual interest is being accrued ?
6. Is this money ring fenced for the original intended use ?
Response
As the information you have requested is 'environmental information' for the purposes of the Environmental Information (Scotland) Regulations 2004 (EIRs), we are required to deal with your request under those Regulations. We are applying the exemption at section 39(2) of the Freedom of Information (Scotland) Act 2002 (FOISA), so that we do not also have to deal with your request under FOISA.
This exemption is subject to the 'public interest test'. Therefore, taking account of all the circumstances of this case, we have considered if the public interest in disclosing the information outweighs the public interest in applying the exemption. We have found that, on balance, the public interest lies in favour of upholding the exemption, because there is no public interest in dealing with the same request under two different regimes. This is essentially a technical point and has no material effect on the outcome of your request.
1. As part of our regular management information release, details of expenditure by financial year are published online. The most recent publication containing information as at 31 March 2026 can be found at the following link: Financial information - Scotland’s Cladding Remediation Programme monthly management information: March 2026 - gov.scot
2 to 5. Under the terms of the exception at regulation 10(4)(a) of the EIRs (information not held), the Scottish Government is not required to provide information which it does not have. The Scottish Government does not have some of the information you have requested. This exception applies to questions 2-5 of your request for the following reasons:
The Scottish Government received £97.1 million in Barnett consequentials for 2021-2022. Barnett consequentials that arise from UK Government’s spending decisions are not ringfenced, and form part of the block grant received by the Scottish Government from the UK Government. Funding for the Cladding Remediation Programme is allocated through the annual Scottish Budget process, therefore information on funding balances, forecasts, location or interest accrued specifically in relation to the consequentials received in 21-22 is not held.
This exception is subject to the 'public interest test'. Therefore, taking account of all the circumstances of this case, we have considered if the public interest in disclosing the information outweighs the public interest in applying the exception. We have found that, on balance, the public interest lies in favour of upholding the exception. While we recognise that there may be some public interest in this information, clearly we cannot provide information which we do not hold.
A breakdown of expenditure from the programme’s single building assessment pilot is available here:
Single Building Assessment programme: spending information - gov.scot
Details of the Scottish Budget for Cladding Remediation 2026 to 2027 are available here:
Chapter 10 Housing - Scottish Budget 2026 to 2027 - gov.scot
6. Barnett consequentials are not ringfenced.
About FOI
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at https://www.gov.scot/foi-responses.
Contact
Please quote the FOI reference
Central Correspondence Unit
Email: contactus@gov.scot
Phone: 0300 244 4000
The Scottish Government
St Andrew's House
Regent Road
Edinburgh
EH1 3DG