Capital infrastructure projects information: FOI release
- Published
- 14 October 2025
- Directorate
- Strategy Directorate
- Topic
- Money and tax, Public sector
- FOI reference
- FOI/202500472654
- Date received
- 24 June 2025
- Date responded
- 22 July 2025
Information request and response under the Freedom of Information (Scotland) Act 2002.
Information requested
You asked for information pertaining to capital infrastructure projects, specifically seeking the following information:
A. A list of all capital infrastructure projects funded by the Scottish Government in 2024–25 which experienced delays in delivery or required a re-profiling of expenditure into future years.
B. For each project listed, please include:
- The original budgeted capital allocation for 2024–25
- The actual capital outturn for 2024–25 (or latest available estimate)
- The stated reason(s) for the delay
- The revised delivery or payment schedule
Response
In relation to request A, I have attached web links to the last two published Major Capital Projects Progress Update reports from August 2024 and February 2025. These six-monthly Scottish Government reports outline the latest progress on the delivery of infrastructure projects with a capital value of £5 million or more which are at the Outline Business Case (or equivalent) approved stage or beyond. The report includes where relevant, any notable project ‘cost’ and ‘time’ variances relating to their planned delivery and the reason for these.
www.gov.scot/publications/major-capital-projects-progress-update-august-2024
www.gov.scot/publications/major-capital-projects-progress-update-february-2025
Under section 25(1) of FOISA, we do not have to give you information which is already reasonably accessible to you. If, however, you do not have internet access to obtain this information from the website(s) listed, then please contact me again and I will send you a paper copy.
In relation to request B, I enclose this information within the following table, noting that the stated reason for any project delays along with any revised delivery schedules, are contained within the enclosed web links to last two published Major Capital Projects Progress Update reports.
Projects within the August 2024 and February 2025 Major Capital Projects Progress Updates which showed an increase in cost and/or a delay in delivery.
|
Project |
Original budgeted capital allocation for 2024-25 |
Actual capital outturn for 2024-25 (or latest available estimate) |
Revised payment schedule |
|
A9 Dualling Tomatin to Moy |
£21.5m |
£15.4m |
£75m in 2025-26. £86.5m in 2026-27. £72m 2027-28. £5.5m 2028-29. £1.5m 2029-30. |
|
East Kilbride Rail Enhancement |
£54.1m See note 1 |
£74.4m See note 2 |
£19.5m in 2025-26 |
|
Markle Level Crossing Bridge Replacement |
£8.7m see note 1 |
£8.5 |
£0.7m in 2025-26 |
|
CMAL - Two new 100 metre ferries |
£60m See Note 3 |
£58.11m See Note 3 |
£37m in 2025-26 |
|
National Waiting Times Centre Board - ospital Expansion Programme - Phase 2 |
See Note 4 |
£5.3m |
See Note 4 |
|
NHS Ayrshire & Arran - Foxgrove (National Secure Adolescent Inpatient Service) |
See Note 4 |
£0.85m |
See Note 4 |
|
NHS Grampian -Aberdeen Baird Family Hospital and ANCHOR Centre |
See Note 4 |
£70.6m |
See Note 4 |
|
NHS Greater Glasgow and Clyde - North East Hub |
See Note 4 |
£3.2m |
See Note 4 |
|
NHS Forth Valley - National Treatment Centre |
See Note 4 |
£0.75m |
See Note 4 |
|
NHS Greater Glasgow and Clyde - Radionuclide Dispensary |
See Note 4 |
£6.47m |
See Note 4 |
|
Dunfermline Learning Campus (College element) |
£51.9m |
£69.4m See Note 5 |
See Note 5 |
|
HMP Highland |
£59.31m |
£43m |
£92.21m in 2025-26. £40.29m in 2026-27. |
|
HMP Glasgow |
£70.89m |
£63.33m |
£252.4m in 2025-26. £374.9m in 2026-27. £239m in 2027-28. £32.1m in 2028-29. |
Notes
1. Rail Enhancement Capital Projects are funded via a portfolio budget. This means that there is no ringfenced funding provided for specific projects so any funding requirements are managed against competing priorities within the overall budget envelope that is provided to us.
2. The capital Outturn for the East Kilbride Rail Enhancement was higher than forecast as work was brought forward from 2025-26, due to the progress being made on construction.
3. Original budgeted capital allocation for 2024-25 was £40m then an additional £20m was allocated at Autumn Budget Revision 2024-25. The capital outturn figure of £58.11m for 2024-25 is provisional and subject to change within the finalised Scottish Government accounts.
4. Capital projects within the Health and Social Care Finance Directorate are funded via a portfolio budget. This means that there is no ring-fenced funding provided for specific projects so any funding requirements are managed against competing priorities within the overall budget envelope that is provided to us.
5. The full £51.9 million allocation for 2024-25 was utilised as planned. However, the actual capital outturn for 2024-25 also included £17.5 million reprofiled from the 2023-24 budget, resulting in a total spend of £69.4 million for the financial year. The budgeted capital allocation for the remainder of the project remains the same and no revised payment schedule is planned.
About FOI
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at https://www.gov.scot/foi-responses.
Contact
Please quote the FOI reference
Central Correspondence Unit
Email: contactus@gov.scot
Phone: 0300 244 4000
The Scottish Government
St Andrew's House
Regent Road
Edinburgh
EH1 3DG