1. Argyll and Bute Council, The City of Edinburgh Council, Glasgow City Council, Fife Council, West Dunbartonshire Council, West Lothian Council, Scottish Borders Council, South Lanarkshire Council, Angus Council, Dumfries and Galloway Council, City of Aberdeen Council, East Renfrewshire Council and East Lothian Council.

2. During 2021 to 2022, the previous 50,000 affordable homes target was met on 23 March 2022, a year later than planned, after delays caused by the COVID-19 pandemic and global issues around supply and workforce affected the pace at which homes could be delivered. The balance of homes delivered during March 2022 signalled the start of progress towards delivering the current 110,000 affordable homes target. Full detail is provided in the 2021 to 2022 out-turn report.

3. BICS weighted Scotland estimates: data to wave 125. This Scottish Government publication is derived from the Business Insights and Conditions Survey (BICS), a monthly survey run by the ONS (Office for National Statistics), which is then weighted to produce estimates for Scotland. Due to sample size constraints, estimates are not available for all Scottish industries.

4. Department for Business and Trade, Building materials and components: monthly statistics.

5. Affordable Housing Supply Programme tables.

6. Office for National Statistics (ONSConsumer price inflation.

7. Figures relating to 2023 to 2024 based on management figures and may be subject to change.

8. Note: the ‘% of Total’ figures provided in the final column are rounded to the nearest whole number which means totals may not sum due to rounding.

9. Scottish Government has since announced £768 million funding for affordable homes in 2025 to 2026 budget

10. The projects reported in this row relate to those approved after 29 October 2021 (when the current benchmark approach was introduced).

11. The benchmarks that were in place in April 2023 were increased in June 2023.