Situation and Compliance Report on the Disposal of Urban Wastewater and Sludge in Scotland 2018
This report provides a summary of the situation regarding the disposal of urban wastewater and sludge in Scotland in 2018. Furthermore, the report assesses compliance with the requirements for the collection and treatment set out in the Urban Wastewater Treatment (Scotland) Regulations 1994.
10. Annex A – Failures against requirements of Regulation 5
|
Agglomeration |
Reason for failure |
Comments |
Proposed Measures |
|---|---|---|---|
|
Aberfeldy |
Regulation 5(1) (Secondary treatment) - Bad Performance |
Fully compliant in 2019 |
N/A |
|
Motherwell |
Regulation 5(2) (Nutrient removal) - Bad Design |
Dosing in place to secure compliance from 1st of April 2019 and the annual average of the samples taken between April 2019 and March 2020 was less than the 2mg/l required standard. |
N/A |
|
Dalmarnock |
Regulation 5(1) (Secondary treatment) - Bad Performance |
Fully compliant in 2019 |
N/A |
|
Kinneil Kerse (Grangemouth) |
Regulation 5(1) (Secondary treatment) - Bad Performance |
Fully compliant in 2019 |
N/A |
|
Melrose |
Regulation 5(1) (Secondary treatment) - Bad Performance |
Fully compliant in 2019 |
N/A |
Reasons for non-compliance must be identified as required by Regulation 12A(2)(b) and proposed measures to achieve compliance must be identified, as per Regulation 12A(2)(c). In all instances, the measures to achieve compliance in 2018 are noted as N/A as non-compliance is rectified the following year.
Contact
Email: waterindustry@gov.scot