4. Processing Agreements
Some local authorities use processing agreements where the developer and the local authority agree on timescales for decisions. Applications subject to a processing agreement are not included in average decision time calculations.
In the final six months of 2019/20 there were 1,193 applications decided that had processing agreements, 170 fewer than in the same period in the previous year.
In quarter three 7.1% of all applications (604 of 8,528) had processing agreements, in quarter four this increased to 7.5% (589 of 7,834) of all applications having a processing agreement.
Quarter 3 | Quarter 4 | |||
---|---|---|---|---|
Category of development | Number of Decisions | % Within Agreed Timescales | Number of Decisions | % Within Agreed Timescales |
Major Applications | 28 | 75.0% | 18 | 55.6% |
Local Applications | 497 | 77.7% | 503 | 80.5% |
EIA Developments | 2 | 50.0% | 0 | - |
Other Consents | 77 | 76.6% | 68 | 75.0% |
Total | 604 | 77.3% | 589 | 79.1% |