Infrastructure Investment Plan 2021-22 to 2025-26: progress report - 2021 to 2022

First annual progress report relating to the Infrastructure Investment Plan 2021-22 to 2025-26 which outlines the progress made in relation to the Plan’s three themes during the last year as well as key delivery achievements and activity planned for the coming year.

This document is part of a collection


Annex C: Major capital projects - climate change targets, strategic outcomes and contribution made to economic development.

The following includes information relating to projects within the IIP Major Capital Projects Progress Update and their accompanying climate change targets, strategic outcomes and the contribution made to local economic development.

Sector: Transport

Project Name: A77 Maybole Bypass

How does the project support the Scottish Government's Climate Change Targets: The project recently achieved an "Excellent" score in its latest CEEQUAL (Civil Engineering Environmental Quality Assessment & Award Scheme Manual) assessment. For domestic waste, the project is committed to zero waste going to landfill, which it is on track to achieve. The construction contract includes provision of an energy management plan, waste management plan, and both environmental and carbon management systems. Low-emission vehicles are being used by the site representatives and client, in line with the contract stipulation that this type of vehicle shall be provided by the contractor.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The inclusion of a positive Sustainable Drainage Systems (SUDs) will improve the drainage in the area thereby controlling the flow of water released into the existing drainage systems thus supporting the mitigation of potential flooding. The project also drives inclusive economic growth by strengthening connectivity; the bypass provides a key link between Scotland's ports and the central belt, enhancing the safety and resilience of Scotland's strategic transport network.

How does the project contribute to Local Economic Development: Overall, the project has provided 6 Modern Apprentice and 5 Graduate Apprentice opportunities, whilst 2 apprentices from the local community employed by the project contractor continue to obtain work experience and training as part of the Graduate Apprenticeship Civil Engineering Scheme, alongside 3 interns studying in their fourth year of University. The project provided 11 site opportunities across admin, document control, community liaison and cleaning. In addition, it provided training placements for senior pupils from local Academies to shadow key project personnel on site.

The local community has benefitted from opportunities created for small and medium enterprises (SMEs) and 27 SMEs have been awarded contracts through the project, the total value of which is £4.3 million. Nine qualifications of SVQ2 and above have been gained with three site based work experiences placements achieved. During peak construction, the site employed 155 people. The economic assessment undertaken as part of the development of the proposed scheme shows that the scheme represents good value for money by generating a positive economic return for investment.

Project Name: A92/A96 Haudagain Junction Improvement

How does the project support the Scottish Government's Climate Change Targets: The project has achieved an "Excellent" Interim Client and Design award from CEEQUAL in the design phase and the project team are seeking to achieve an "Excellent" whole project award rating for the construction phase. Prior to the main works construction contract commencing, an advance works demolition contract resulted in the recycling of over 97% of the demolition material. The construction contract includes provision of an energy management plan, waste management plan, and both environmental and carbon management systems. Low-emission vehicles are being used by the site representatives, in line with the contract stipulation that this type of vehicle shall be provided by the contractor

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The project includes positive Sustainable Drainage Systems (SUDs) as described above for A77 Maybole Bypass. The project provides improved transport opportunities and enables the local area to be regenerated supporting inclusive development. The new infrastructure provides relief and resilience to the local transport networks enabling people and communities to be better connected.

How does the project contribute to Local Economic Development: The new dual carriageway link road will help tackle the congestion caused by the traffic bottleneck at the Haudagain roundabout and deliver significant benefits including improving traffic flow, alleviating congestion and improving journey time reliability for road users and public transport.

The opportunity to secure wider benefits for the economy beyond the traditional project objectives linked to the procurement of transport infrastructure is recognised, and community benefit requirements are included in this contract. Scottish Government works contracts are already being utilised where appropriate to secure training and employment opportunities through the use of targeted recruitment and training clauses. These clauses are incorporated into the contract documents for Haudagain. Project includes a Project Bank Account to improve payment timescales for the supply chain.

The project has provided 145 community engagement activities, 16 work placements for school pupils, college and university students and employment opportunities for 7 apprentices and 5 graduates. Two previously long-term unemployed individuals, one of whom lives local to the project, were employed as full time permanent contractors' staff. In addition, 17 sub-contracts awarded on the project have been to SME's, two of which were awarded to a supported business or social enterprise.

Project Name: A9 Dualling: Luncarty to Pass of Birnam

How does the project support the Scottish Government's Climate Change Targets: The project has created approximately 4 km of new and upgraded pedestrian, equestrian and cycle routes, helping to promote sustainable and active transport, linking the communities of Luncarty and Bankfoot for the first time. In addition, sections of the existing core paths within the project area have also been upgraded with new asphalt surfacing and mounting blocks have been installed at key locations to improve access for equestrians to encourage more active travel within the route corridor, providing safe, segregated routes for pedestrians, cyclists and equestrians.

The construction contract included provision of waste and carbon management plans on site with the aim of minimising the environmental impact of the construction process. The waste produced from the project was carefully segregated and recycled with huge volumes of materials reused onsite, meaning 99% of site waste was diverted from landfill. The project also used innovative environmentally friendly practices for items such as non-metal based coagulants for surface water treatments and non-plastic tree shelters, which further assisted in protecting the environment.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The project included positive Sustainable Drainage Systems (SUDs), as described above for A77 Maybole Bypass. The project helped to drive inclusive economic growth by strengthening connectivity; the dual carriageway reduces journey times and improves journey time reliability along this part of the A9 corridor. This will improve the competitiveness of rural businesses.

This project has helped improve the economic, social and environmental wellbeing of the surrounding communities, by providing training and employment opportunities, fair working practices, promotion of equality, supporting small to medium enterprises and charities. The project has maximised employment and work placements, delivered skills and training to support young people at school, colleges and universities, and has inspired and encouraged careers using science, technology, engineering and mathematics (STEM) within the next generation of engineers.

How does the project contribute to Local Economic Development: During construction, the project provided the following:

  • 44 sub-contracts awarded to Scottish businesses with value of £34.4 million, (40 of them SME 40 – with a value of £17.25 million)
  • 65 new job opportunities and 65 work experience placements
  • Engagement with 4,046 school pupils and further education students
  • 50 days of volunteering to support grass root community initiatives
  • Donations of more than £13.6k to local good causes from our contractor for the project, Balfour Beatty and its sub-contractors

Project Name: A9 Dualling Tomatin to Moy

How does the project support the Scottish Government's Climate Change Targets: Every effort is being made to mitigate the environmental impacts of this programme. We value the environment we are working in and place emphasis on striking a balance between delivering projects and respecting the sensitivities of the area. Significant environmental assessment work and consultation has been undertaken to consider environmental impacts for this programme.

Our National Transport Strategy is clear that we will not build infrastructure to cater for forecast unconstrained increases in traffic volumes. The rationale for investment in this project is not based on facilitating increases in road traffic. We will continue to take bold action to reduce both car usage and the emissions of road vehicles. Contract requirements will include a focus on carbon reduction, use of renewable power sources, use of low emission vehicles and construction plant, emphasis on waste reduction and circular economy and exploration of innovative alternative design solutions.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The project will drive inclusive economic growth by strengthening connectivity; the dual carriageway reduces journey times and improves journey time reliability along this part of the A9 corridor. This will improve the competitiveness of rural businesses using the A9

The contract will include an emphasis on sustainability; economic growth and building resilient and sustainable places. It will include increased focus on decarbonisation, including increased carbon reduction measures, waste management controls and material reuse (circular economy) proposals, particularly in relation to peat. The contract will also contain a provision for the site accommodation to be a "sustainable power hub", with the main source of energy coming from the national grid (i.e. from renewable sources rather than fossil fuel generators).

The project will include the use of positive Sustainable Drainage Systems (SUDs) to improve the drainage in the area thereby controlling the flow of water released into the existing drainage systems, and providing treatment to water runoff. This will support the mitigation of potential flooding, treat water at source and provide ecological benefits.

There will also be an emphasis placed upon opportunities generated for Small and Medium Enterprises and Supported Businesses, to help support economic growth in the region. It will also provide training opportunities, fair working practices and promotion of equality and wellbeing for all people working on the project. The appointed contractor will also propose a number of community enhancements in and around the project to provide lasting benefits for local communities.

How does the project contribute to Local Economic Development: The contract will include a significant emphasis on community benefits and social value. Such benefits are envisaged to include creation of employment and training opportunities, including an on-site training facility to be shared with communities surrounding the project, supporting small and medium sized enterprises through local subcontract opportunities and maximising opportunities for Supported Businesses and Social Enterprises as well as an emphasis on improving health and wellbeing of workforce.

The project also aims to provide educational benefits to local schools through training initiatives such as Academy 9 programme. It also aims to provide local communities with improved connectivity to public transport with upgrades to approximately 10km of non-motorised user routes to encourage active travel such as walking and cycling.

Project Name: Reston and East Linton Rail Stations

How does the project support the Scottish Government's Climate Change Targets: The National Transport Strategy 2 (NTS2) was published in February 2020 and outlines the vision for Scotland's transport system over the next 20 years. One of the 4 priorities on NTS2 is taking climate action. The scheme encourages an increase in rail patronage within Reston, East Linton and the each of the surrounding areas and subsequently encourages more sustainable trip making. The project thus contributes towards Net Zero and Environmental Sustainability by enabling modal shift from road to rail.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The development supports the SPP (Scottish Planning Policy) overriding goal of achieving sustainable development by providing a high-quality rail connection to strategic locations such as Edinburgh (north) and Berwick-Upon-Tweed (south). This will contribute towards the policy of driving inclusive economic growth.

Reston represents the most rural area within the Scottish Borders. The Scottish Index for Multiple Deprivation 2020 shows that nearby towns such as Eyemouth, Duns and Coldstream have small pockets of relative deprivation within their communities, which suggests that employment and further education opportunities for these communities are limited.

The provision of a station at Reston would improve public transport access times to Edinburgh and open up work and study opportunities for the local population. This will subsequently enhance economic prosperity across Berwickshire and provide an impetus for community regeneration. Therefore, this new station has the potential to support Berwickshire in meeting the strategic priorities set out within NTS2. Each of the new stations will also facilitate new sustainable housing developments at East Linton and Reston, thus contributing the theme of Building Resilient and Sustainable Places.

How does the project contribute to Local Economic Development: The project will be delivered by Network Rail, with BAM Nuttall as the main contractor. Both of these organisations employ graduate trainees and have extensive apprentice training programmes.

Project Name: East Kilbride Rail Enhancement

How does the project support the Scottish Government's Climate Change Targets: The project aligns with Scotland's 2018-2032 Climate Change Plan update. It also takes climate action; helping to deliver the net-zero target, adapting to the effects of climate change and promoting greener, cleaner choices. Decarbonised corridors will help to deliver the net-zero target.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Delivering the East Kilbride project allows decarbonisation in the form of electrification on this region of the network, which will be enabled through the deployment of existing electric rolling stock. As well as delivering the full electrification of the East Kilbride corridor, the project will also deliver enhanced station facilities at East Kilbride and the construction of the new, relocated Hairmyres station with enhanced facilities, which will be transformational in providing a bus interchange, park and ride and active travel hub for passengers along this vital route. Step free access is to be provided at both these stations, and Giffnock station, enhancing accessibility for passengers.

How does the project contribute to Local Economic Development: To be confirmed following FBC approval and Network Rail's engagement with contractors.

Project Name: Levenmouth Rail project

How does the project support the Scottish Government's Climate Change Targets: The project will contribute to the Transport Scotland's National Transport Strategy 2S target of a reduction in carbon emissions by 75% compared to the baseline by 2030 and decarbonisation by 2035, as well as towards net-zero greenhouse gas emissions by 2045. The project has the opportunity to encourage modal shift from private car to rail, especially for journeys within Levenmouth, contributing to reducing carbon emissions. The project will provide opportunities to increase the sustainable mode share and support a reduction in carbon emissions.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: New opportunities for travel will be opened up to provide access to additional jobs, educational facilities and connectivity for leisure activities, accessibility and other local attractions. The project will also increase the attractiveness of Leven for increased economic activity and tourism through increased labour market participation and productivity uplift.

How does the project contribute to Local Economic Development: The reinstatement of Levenmouth Rail Line will provide the area with a major boost to economic sustainability and connectivity. It will deliver opportunities for local people - unlocking access to education, culture, entertainment and employment options, as well attracting new business and investment. This is further enhanced by the £10 million Levenmouth Reconnected Programme which seeks to maximise the economic and social opportunities presented by the new Levenmouth Rail Line.

Project Name: Inverness Airport Station (formerly called Dalcross Station)

How does the project support the Scottish Government's Climate Change Targets: The project's outputs will enable airport passengers and employees to reach the airport via public transport with lower per capita CO2 emissions than by travelling to the airport by car.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: By providing a greener method for people to travel to Inverness Airport, the project will be helping to enable the transition to Net Zero Emissions and Environmental Sustainability. By helping to bring people to the Inverness Airport Business Park, the project will be driving inclusive economic growth and boosting productivity and competitiveness. By providing a station for the nearby new town of Tornagrain, the project will be contributing to building resilient and sustainable places.

How does the project contribute to Local Economic Development: Network Rail and BAM, NR's principle contractor for the project, both employ graduate trainees and take on apprentices. Project will help bring people to Inverness Airport Business Park, driving inclusive economic growth and boosting productivity and competitiveness

Project Name: Barrhead Rail Enhancement

How does the project support the Scottish Government's Climate Change Targets: The project aligns with Scotland's 2018-2032 Climate Change Plan update. It also takes climate action; helping to deliver the net-zero target, adapting to the effects of climate change and promoting greener, cleaner choices. Decarbonised corridors will help to deliver the net-zero target. Achieving broader transport decarbonisation, through mode shift resulting from increased service frequency between Barrhead and Glasgow, will further help to deliver the net-zero target.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The scheme is going to deliver the following outcomes:

  • Decarbonised railway on the Glasgow to Barrhead corridor. Delivery of Glasgow to Barrhead decarbonisation is the first stage of electrification on the GS&W freight trunk route. In addition, the electrification of the Glasgow to Barrhead corridor is required to:
  • Deliver on STPR2 commitments
  • Act as a key enabler to the wider decarbonisation strategy
  • Support East Kilbride route decarbonisation
  • Enable interim decarbonisation to Kilmarnock via battery electric trains
  • Greener, quieter, comfortable, reliable electric trains
  • Increase in passenger capacity via new Strathclyde Fleet (arrives 2026/27)
  • Enhanced accessibility opportunity across all stations

How does the project contribute to Local Economic Development: To be confirmed following Network Rail's engagement with contractors.

Project Name: CMAL - Two new 100 metre ferries

How does the project support the Scottish Government's Climate Change Targets: This project aligns with Scotland's 2018-2032 Climate Change Plan Update. Contributing towards a reduction in carbon emissions by the use of Liquefied Natural Gas (LNG) and bunkering facilities at ports. LNG is a proven technology, utilised by maritime sectors in a number of other countries, including Norway. The LNG facility will be built in line with industry and safety requirements. LNG has a reduced GHG (Greenhouse Gas) emission compared to MGO (Marine Gas Oil) of c.20-25%.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The project is going to deliver the following:

  • LNG has significant local air quality benefits with shore-powering providing for overnight powering of vessels, with significant local noise and air quality improvements for residents and crew
  • Act as a key enabler of the wider net-zero vessel strategy
  • Greener, quieter, reliable vessels on Scotland's ferry network

How does the project contribute to Local Economic Development: These new ferries will improve the ferry service provision to island communities. It is anticipated these new ferries will boost economic sustainability through tourism. In addition, they will also maintain and enhance social and cultural wellbeing and the sustainability of these communities. This can also include direct access to jobs and access to services such as health and education.

Sector: Health

Project Name: NHS Grampian - Aberdeen Baird Family Hospital and ANCHOR Centre

How does the project support the Scottish Government's Climate Change Targets: The targets for both Thermal and Electrical load for both new buildings have been set at a level which is lower per m2 than the buildings which they are replacing therefore this is a reduction and working towards net zero carbon.

The buildings will be sourcing their heat for a Low Zero Carbon district heating scheme from the campus centrally in the form of a CHP (Combined Heat and Power). Flood risk assessment was undertaken and informed the design. The Board works towards aligning itself with all government legislation and adhering to the targets.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Improvements in Energy Performance and Carbon Reduction of the new facilities will support the delivery of national targets and the NHS Grampian's Carbon Management Plan. The priority of NHS Grampian to tackle health inequalities has been recognised in the development of this project for example: the use of technology to deliver services in local communities where possible; promoting home or community based treatment, and the creation of Community Maternity Units – in Aberdeen, Inverurie and Peterhead.

How does the project contribute to Local Economic Development: Community benefits recorded as achieved include:

  • Number of new jobs supported by project on a Quarterly basis - 6
  • Advanced Health and Safety Training - Principal Supply Chain Partners (PSCP) to deliver H&S training to advanced level - 20
  • Meet The Buyer Events - Focus on Tier 2 supply chain - 2
  • Apprenticeship in employment on project at any level (Existing Apprentices) - 15
  • Apprenticeship Completions - whilst working on project - 1
  • Graduate Employment - 4
  • Employment Opportunities - minimum of 26 weeks and aimed at and filled by New Entrants - 6
  • Work Experience Placements - 7
  • School visits (primary and secondary) - presentation on careers and project - 102

Project Name: NHS Highland - Redesign of Services for Skye, Lochalsh & South West Ross

How does the project support the Scottish Government's Climate Change Targets: The design of the new hospital predates the current Carbon Net Zero targets. However, the new facility is expected to achieve BREEAM (Building Research Establishment's Environmental Assessment Method) excellent and EPC B, which is a substantial improvement on current facilities.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Improved energy efficiency will support the drive to reduce carbon consumption and the site will deliver improved active travel infrastructure and will bring public transport virtually to the front door.

The new hospital will be far more resilient in terms of internal services, with increased capacity and compliant spaces delivering a more reliable, modern and dignified setting for patients which can accommodate new developments in technology.

How does the project contribute to Local Economic Development: The following community benefits targets have been achieved during the new hospital construction phase:

  • Community benefits - donations to local charities, newsletters, 2 school engagement visits, 6 construction careers sessions
  • Training & Education benefits - 13 existing and 2 new start apprentices supported by the project, 2 'qualifying the workforce' qualifications, 2 graduates recruited and 10 student work placements
  • Employment benefits - 7 new jobs created, 3 new jobs with SMEs within hub North territory, 1 new job with SME within Scotland
  • Economic benefits - £11.6 million work awarded to SMEs within hub North territory, £5.1 million work awarded to SMEs in rest of Scotland, £0.5 million of work awarded to other SME within UK. 144 Tier 2 tender enquiries, of which 67 were within hub North territory and 55 were elsewhere within Scotland

Some planned benefits could not be achieved due to COVID-19 restrictions.

Project Name: NHS Highland - Redesign of Services for Badenoch and Strathspey

How does the project support the Scottish Government's Climate Change Targets: The New Badenoch & Strathspey Community Hospital was already in construction when Net Carbon Zero target was announced but nevertheless delivers a significant improvement on current, dated facilities. The new hospital is expected to achieve BREEAM Excellent and EPC band B, which is a substantial improvement on performance of existing facilities.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Improved energy efficiency will support the drive to reduce carbon consumption and the site will deliver improved active travel infrastructure and brings public transport virtually to the front door. The new hospital will be far more resilient in terms of internal services, with increased capacity and compliant spaces delivering a more reliable, modern and dignified setting for patients which can accommodate new developments in technology.

Consolidating two inpatient facilities, a health centre and separate office facility into one building creates a more sustainable staffing model and provides better opportunities for staff to communicate between teams.

How does the project contribute to Local Economic Development: The following community benefits targets have been achieved during the new hospital construction phase:

  • Community benefits - donations to local charities, newsletters issued, 2 school engagement visits, 6 construction careers sessions;
  • Training & Education benefits - 15 existing and 2 new start apprentices supported by the project, 2 'qualifying the workforce' qualifications, 1 graduate recruited, 10 student work placements and 15 work experience placements (14-19yrs)
  • Employment benefits - 12 new jobs created, 4 new jobs with SMEs within hub North territory, 1 new job with SME within Scotland
  • Economic benefits - £11.6 million work awarded to SMEs within hub North territory, £5 million work awarded to SMEs in rest of Scotland, £361k of work awarded to other SME within UK. 139 Tier 2 tender enquiries, of which 51 were within hub North territory and 75 were elsewhere within Scotland

Some planned benefits could not be achieved due to COVID-19 restrictions.

Project Name: NHS Greater Glasgow and Clyde - Clydebank Health & Care Centre

How does the project support the Scottish Government's Climate Change Targets: Clydebank Health Centre will link into the Queens Quay District Heating system towards the end of 2022

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Queens Quay is West Dunbartonshire Council's key regeneration project. Its aim is to provide a better environment for the people of Clydebank and importantly to attract new residents and families to a regenerated riverside location. The wider Queens Quay site has planning permission for mixed-use development comprising a predominantly residential development to the west with a mix of retail, commercial and leisure uses around the basin and a health quarter to the north of the basin.

How does the project contribute to Local Economic Development: The provision of local employment and training opportunities together with a significant contribution to the regeneration strategy set out for Queens Quay Regeneration Masterplan.

Project Name: National Waiting Times Centre Board - Hospital Expansion Programme - Phase 2

How does the project support the Scottish Government's Climate Change Targets: Project delivered in line with current sustainability guidance, BREEAM 2018. Targets agreed with NSS / HFS (National Services Scotland / Healthcare Frameworks Scotland) as part of key stage reviews.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Zero carbon was not mandated when the project was being developed. The building will be energy efficient with energy targets agreed. Economic growth will be driven by use of local supply chain where appropriate - contractor has community benefit criteria to meet in this regard. Phase 2 of the Hospital Expansion Programme will increase capacity and provide better long-term service provision.

How does the project contribute to Local Economic Development: Project will provide opportunities on Employment, Skills & Training, Health Benefit Outcomes, Environmental issues, SME & 3rd Sector Involvement in line with our board policies Better Health Through Employment, Sustainability / Environmental and Procurement Strategy.

Project Name: NHS Grampian - National Treatment Centre

How does the project support the Scottish Government's Climate Change Targets: The targets for Thermal and Electrical load for each building have been set at a level which is lower per m2 than the buildings which they are replacing therefore this is a reduction and working towards net zero carbon. Flood risk assessment was undertaken and informed the design. The Board works towards aligning itself with all government legislation and adhering to the targets.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Improvements in Energy Performance and Carbon Reduction of the new facilities shall support meeting national targets and the NHS Grampian's Carbon Management Plan. The priority of NHS Grampian to tackle health inequalities has been recognised in the development of this project.

How does the project contribute to Local Economic Development: The development is of a significant scale and local jobs will be secured and new jobs provided as a result.

Project Name: NHS Lothian - National Treatment Centre

How does the project support the Scottish Government's Climate Change Targets: The national and international context for Net Zero Carbon (NZC) buildings could not be clearer and the Board fully accept the challenge to design hospitals with NZC emissions over their lifetime embracing their construction, operation and eventual end of life and disassembly. Recognising that construction does carry a heavy price in carbon emission, the Board's aim is therefore to minimise operational and embodied energy and associated carbon emissions, which then minimises the cost of offsetting the associated carbon through zero carbon generation, zero carbon energy tariffs or recognised energy offsetting schemes. All steps will be taken to ensure the facility is future proofed to accommodate early adoption of appropriate technology and infrastructure.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The National Treatment Centre will have a significant positive impact on project stakeholders (NHS Lothian, Regional Boards, patients, staff and partners) and on the wider economy, environment and communities. The identification of benefits contributing to a socially inclusive, 'net zero carbon economy' is key in the decision making process.

The Scottish Government's National Performance Framework has been used to provide a structure to the identification, incorporation and assessment of these wider economic benefits to demonstrate the benefit of the project to communities and economy of Lothian.

How does the project contribute to Local Economic Development: The project will provide skilled employment opportunities for the local area through its lifecycle from construction to operation, with Key Performance Indicators (KPIs) as part of the Framework Contract. It will also attract skilled workers to the area further contributing to the development of the local economy.

Project Name: NHS Lothian - Reprovision of Eye Services

How does the project support the Scottish Government's Climate Change Targets: The national and international context for Net Zero Carbon (NZC) buildings could not be clearer and the Board fully accept the challenge to design hospitals with NZC emissions over their lifetime embracing their construction, operation and eventual end of life and disassembly. Recognising that construction does carry a heavy price in carbon emission, the Board's aim is therefore to minimise operational and embodied energy and associated carbon emissions, which then minimises the cost of offsetting the associated carbon through zero carbon generation, zero carbon energy tariffs or recognised energy offsetting schemes. All steps will be taken to ensure the facility is future proofed to accommodate early adoption of appropriate technology and infrastructure.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The Reprovision of Eye Services will have a significant positive impact on project stakeholders (NHS Lothian, Regional Boards, patients, staff and partners) and on the wider economy, environment and communities. The identification of benefits contributing to a socially inclusive, 'net zero carbon economy' is key in the decision making process. The Scottish Government's National Performance Framework has been used to provide a structure to the identification, incorporation and assessment of these wider economic benefits to demonstrate the benefit of the project to communities and economy of Lothian.

How does the project contribute to Local Economic Development: The project will provide skilled employment opportunities for the local area through its lifecycle from construction to operation, with KPIs as part of the Framework Contract. It will also attract skilled workers to the area further contributing to the development of the local economy.

Project Name: NHS Highland – National Treatment Centre

How does the project support the Scottish Government's Climate Change Targets: The National Treatment Centre (NTC-H) will provide elective surgery to the population of the North of Scotland. This will reduce the number of journeys taken by patients and their families/carers from the North of Scotland to access services in the central belt. The NTC-H will provide an energy efficient building with a Building Management System, which supports effective management of the building. The site supports 'active travel' through provision of secure bicycle shelters and staff changing facilities. The site is designed to allow access for local bus companies, and a bus shelter is included on the Campus. There are Electric Vehicle charging points included for use by staff/patients/visitors.

The NTC-H has been in construction since July 2020 when Net Carbon Zero targets was announced but nevertheless delivers a significant improvement on current, dated facilities. The NTC-H is targeting a BREEAM 'Very Good' rating, and this was agreed with HFS during the NHS Scotland Design Assessment Process.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Improved energy efficiency will support the drive to reduce carbon consumption, and the site will deliver improved active travel infrastructure and brings public transport virtually to the front door. The new hospital will be far more resilient in terms of internal services, with increased capacity and compliant spaces delivering a more reliable, modern, and dignified setting for patients, which can accommodate new developments in technology.

The NTC-H is located on the Inverness Campus. From the outset, the NTC-H project was developed in collaboration with local partners (Highland and Islands Enterprise (HIE) and University of Highlands and Islands (UHI)) to maximise opportunity for joint investment, innovation, and develop collaborative arrangements for training, education, research & development. This collaborative working aims to contribute to economic and social needs of rural and island areas through improving access for education and training, creating opportunity for research and development companies to work with clinicians and patients, and for the location of the NTC-H to support the aims and objectives of the Inverness Campus developed by HIE.

The NTC-H provides healthcare staff with an opportunity to work with a 'best in class' target operating model within a modern, compliant, and technologically enabled environment which will provide an attractive proposition in recruiting and retaining staff, thus contributing to the sustainability of the Highland region.

How does the project contribute to Local Economic Development: Providing a new National Treatment Centre in Inverness will contribute to recruitment and retention of staff within the Highlands. The construction project has contributed significantly to local business and in particular construction contractors and material suppliers. The contractor building the NTC-H are delivering on their Community Benefits obligations which include:

  • Providing opportunities to support local civil engineering students at UHI
  • Membership of the Inverness College Industry Advisor Board
  • A 5-week virtual work experience for local secondary schools
  • Engaging with local Youth Employment Services Group

Project Name: NHS Fife - Elective Orthopaedic Centre

How does the project support the Scottish Government's Climate Change Targets: Project delivered in line with current sustainability guidance - BREEAM 2018. Targets agreed with NSS / HFS (National Services Scotland / Healthcare Frameworks Scotland) as part of key stage reviews.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Zero Emissions and Environmental Sustainability: Zero carbon was not mandated when the project was being developed. The building will be energy efficient with energy targets agreed with NSS and HFS as part of the key stage review process. The building makes use of existing energy sources from the retained estate. A wider low carbon, sustainable masterplan for the retained estate will be pursued as part of the board's property and asset management strategy.

Economic growth: In the short term, the project will support economic growth through construction activity in the local market supporting local supply chains and encouraging development opportunities for the young via schools and colleges. A community benefits register will help to deliver these aims. In the longer-term, the new centre with a third theatre and supporting outpatient and inpatient accommodation will help to drive job growth within orthopaedics.

Resilient and sustainable places: the new centre is being created to rectify environmental issues with the existing facility and to provide sufficient capacity for the local people of Fife over the longer-term. The new facility may also offer opportunities for Regional partners to make use of any residual capacity providing more orthopaedic resilience within Scotland overall.

How does the project contribute to Local Economic Development: In the short term, the project will support economic growth through construction activity in the local market supporting local supply chains and encouraging development opportunities for the young via schools and colleges. A community benefits register will help to deliver these aims. In the longer-term, the new centre with a third theatre and supporting outpatient and inpatient accommodation will help to drive job growth within orthopaedics.

Project Name: NHS Forth Valley - National Treatment Centre

How does the project support the Scottish Government's Climate Change Targets: Will align to an existing hospital project agreement and tie into existing infrastructure. It is intended to invest NHS Board capital in the installation of Photovoltaic Panels on the roof of the new ward. The project will be delivered in line with target BREEAM rating to be agreed with NSS / Health Facilities Scotland.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Reducing Patient Waiting Times while also localising treatments.

How does the project contribute to Local Economic Development: As a modular building, manufacture will be offsite with enabling work and construction separately as well as car parking construction and amendments. Opportunities for local economic development are to be confirmed with the SPV (Special Purpose Vehicle) and contractors.

Project Name: NHS Western Isles – Barra and Vatersay Community Campus

How does the project support the Scottish Government's Climate Change Targets: To be confirmed as project development is currently on hold.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: To be confirmed as project development is currently on hold.

How does the project contribute to Local Economic Development: To be confirmed as project development is currently on hold.

Project Name: NHS Greater Glasgow and Clyde - North East Hub

How does the project support the Scottish Government's Climate Change Targets: Glasgow City Council introduced a Gold Standard for Planning Applications in 2019 that similarly required net zero carbon developments. The design proposals for North East hub and accompanying cost plans have been developed to achieve this through rigorous examination of design, specification and construction proposals. The current design will offer a zero-carbon heating by utilising air source heat pumps and utilising electricity generated by photovoltaic panels and green electricity from the grid. The building fabric includes passivhaus principles of high air-tightness requirements and heat recovery from ventilation systems. Triple glazing is used throughout with a presumption towards using natural light and natural ventilation where possible.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The success of this investment in enabling service transformation for the benefit of the local community will be demonstrable through delivery of these opportunities and benefits whilst also becoming integral to further regeneration plans for the area, fostering inclusive carbon net zero economic growth, producing an even more resilient community who have a focus on "place making", becoming a fairer and more equal society, and reducing poverty and inequalities

How does the project contribute to Local Economic Development: A community investment group has been set up to help develop the social value plan for the North East Hub project. Key outcomes to date include:

  • 2 new start employment opportunities have been created on site. These were advertised via Jobs and Business Glasgow and the transitional employment programme was utilised
  • Education programme launch November 2021, supporting 13 pupils through their Foundation Apprenticeship at SCQF level 4 in Construction
  • Helping Hands Initiative Competition launched July 202
  • SME local business training, 2 events delivered during Q2 2021 to registered companies

Project Name: NHS Lothian - Oncology Enabling Projects, Edinburgh Cancer Centre

How does the project support the Scottish Government's Climate Change Targets: The majority of the projects within the program are refurbishment projects with limited opportunity for implementation of the net zero carbon strategy. For the new build Linacc project the building has been design in line with the 'fabric first' approach achieving standards above Section 6 Building Regulations. Mechanical and Electrical proposals have incorporated energy efficient building services design features.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The project will provide skilled employment opportunities for the local area through its lifecycle from construction to operation, with KPIs as part of the Framework Contract. It will also attract skilled workers to the area further contributing to the development of the local economy.

How does the project contribute to Local Economic Development: The project will provide skilled employment opportunities for the local area through its lifecycle from construction to operation, with KPIs as part of the Framework Contract. It will also attract skilled workers to the area further contributing to the development of the local economy.

Project Name: NHS Ayrshire & Arran - National Secure Adolescent Inpatient Service

How does the project support the Scottish Government's Climate Change Targets: Foxgrove has been designed to meet Section 6 of the current Scottish Building Regulations, including utilising the "hotbox" of existing boilers to provide a district heating system for Foxgrove. This is classed as an innovative way to reuse waste energy from the existing boilers.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Recycled Waste (% Target to be set). Reduced Waste to Landfill (% of re-use inert material, Target to be set). Carbon Reduction (Car sharing scheme, training and awareness workshops to building users on efficient use of building, deliver cycling proficiency training).

How does the project contribute to Local Economic Development:

  • Works Awarded by Value (5% of works awarded to SMEs by value)
  • Work Awarded by Tendering Opportunities to SMEs (20%)
  • Supplier Development e.g. Number of seminars (winning work, value management, risk management, PQQ bidding, Health and Safety, environmental stewardship etc)
  • 1 Meet the Buyers Day
  • 15 Training sessions provided to SMEs e.g. Number of seminars (leadership, supervisor, Health and Safety, presentation, BIM, bid training etc)

Project Name: NHS Tayside - Electrical Infrastructure Zone 2 - Radiotherapy, Maternity and West Ward Block

How does the project support the Scottish Government's Climate Change Targets: Energy efficient lighting to all new areas covered by the project and the area has been designed to the Scottish Technical Standards in terms of U-values and Air Leakage.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Project incorporates the following within the design (a) Transformers that incorporate amorphous core technology. The Wilson e3 transformers proposed have the lowest combined losses that meet EU Eco-Design requirements (b) Replacement of the existing 50-year-old generator with modern efficient machines (c) Sedum ('Living') roof – Slows down water going to drain and absorbs CO2. (d) SUDS – Installed over part of the site adjacent to the new generator building.

The Principle Supply Chain Partner (PSCP) has a significant number of SME contractors from the local geographical area throughout the duration of the project. 'PSCP' has provided a number of their own staff for volunteering days to upgrade an existing hospital courtyard for future use by patients and staff. Project is upgrading in part the 50-year-old HV Network along with N+1 resilience providing 100% back up of all electrical services within the zone via the installation of 2 no. 1MVA generators.

How does the project contribute to Local Economic Development: There a number of community benefits created through this project such as New Employment Opportunity, apprentices, work experience opportunities and local charity fundraisers.

Project Name: NHS Tayside - Children's Theatre Suite Project including the Multi Storey Plant Room

How does the project support the Scottish Government's Climate Change Targets: Area being refurbished was originally constructed in the 1970's. All demolition materials were segregated to allow recycling. Area has been brought up to 2020 Technical Standards levels in terms of u-values, air leakage, LED lighting, environmental controls, energy management, etc. New facility is connected into hospital main heating system, which is now complemented, by Combined heat and power (CHP) infrastructure.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Heating and hot water is via a hospital wide CHP infrastructure. New facility is connected into the new Ninewells Electrical Zone Infrastructure to provide high levels of electrical resilience. All areas of the new facility have been designed to encourage digital connectivity either by patients, or by staff. Flood wired with hard wiring and wireless technology.

How does the project contribute to Local Economic Development: There is a number of community benefits created through this project such as New Employment Opportunity, apprentices, work experience opportunities and local charity fundraisers. The 'Oor Wullie' sculpture trail was highly successful in both raising funds and also encouraging the people of Tayside to get out and about exploring the local environment to see all the different sculptural pieces. Principle Supply Chain Partner (PSCP) 'Meet the Buyer' events held. PSCP has a significant number of SME contractors from the local geographical area throughout the duration of the project. PSCP has also provided a number of their own staff for volunteering days to upgrade an existing hospital courtyard for future use by patients and staff.

Project Name: NHS Tayside - Ninewells Electrical Infrastructure Zone 3

How does the project support the Scottish Government's Climate Change Targets: The Design Team are currently preparing high level designs (incorporating lesson from Zone 1 and Zone 2) and technical solutions to take account of the Net Zero Carbon requirement which will in turn confirm final location and scope of the project to inform any contribution to Climate Change Targets.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: This will be confirmed once a brief has been confirmed for this Zone and designs have commenced.

How does the project contribute to Local Economic Development: As this is a Framework Scotland 3 project, there a number of community benefits created through this project such as New Employment Opportunity, apprentices, work experience opportunities and local charity fundraisers.

Project Name: NHS Ayrshire & Arran - National Treatment Centre - Ayrshire & Arran

How does the project support the Scottish Government's Climate Change Targets: Net Zero policy added to project brief.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Driving Inclusive Growth - NHS Ayrshire & Arran are an anchor institution within the Ayrshire Community Wealth Building strategy. Procurement will target economic opportunities within Ayrshire where possible and incorporation of community benefits. Location adjacent to University Hospital Ayr is consistent and supportive of sustainable places. UHA is proposed to be a centre of elective care under the Caring for Ayrshire strategy.

How does the project contribute to Local Economic Development: This will be developed through the preparation of the FBC.

Sector: Further Education

Project Name: Dunfermline Learning Campus (College element)

How does the project support the Scottish Government's Climate Change Targets: Fife College is continuing to progress up to Decision Point 4: Pre-construction assessment (signature & financial close) recognising this will be to deliver the proposed Hybrid plus low carbon solution to enable the College to achieve net zero emissions. This would allow the college DLC (Dunfermline Learning Campus to be designed and built to be equivalent of Passivhaus standard and also keep the project on the path to being net zero by 2030.

Adopting the Hybrid plus solution will enable the College to implement a range of energy saving measures, in particular to the building elements during construction, which would otherwise be unavailable once the building is completed and in-use. The college DLC project aims to be an exemplar building for the college sector in Scotland and beyond, setting the standard for future college developments.

By progressing with the Hybrid plus design, it will deliver a highly energy efficient building with low embodied carbon which will enable the College to:

  • achieve their net zero emissions target for the campus by 2030
  • deliver operational costs of circa 36% less than that being experienced on recently completed college projects and over 32% better than a design to meet current legislation
  • allows the College to deliver on the Scottish Government's Heat in Buildings strategy by delivering next zero heat at the Campus by 2030
  • delivers upon the Government targets for 2045, setting a sector exemplar model for embodied and operational energy, and deploy
  • an all-electric solution adopted will allow the College to take advantage of green energy and avoid the inevitable increased operational costs that gas fuelled buildings will face in the future

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: Transition to a Net Zero Economy and Environmental Sustainability: Fife College is a pathfinder project for SG's Net Zero Public Sector Building Standard (NZPSB Standard). The College has followed through and produced a Hybrid plus solution (as described under climate change column).

Driving inclusive Economic Growth: The new college campus provides a modern learning facility that is located in the centre of an area that is the fastest population growth in Scotland. The new campus will significantly enhance the degree of collaboration between senior phase school and the College, particularly through the implementation of Learner Pathways which will be delivered jointly by the schools and College, and supported by external stakeholders e.g. Skills Development Scotland (SDS), NHS Fife. It will also provide a step change to increase opportunities for employer and industry engagement through spaces offering more flexible, blended and on-line delivery.

The planned digitalisation and innovation spaces will support engagement activities, knowledge transfer and curriculum alignment with industry needs. The new campus will further enhance the College's ability to engage with university partners in both teaching, innovation and knowledge exchange. In short it will provide Fife College with a transformative and future proofed Place of Lifelong Learning'.

Building Resilient and sustainable places: The FBC is for a new campus for West Fife, as part of the wider DLC campus development, working in partnership with Fife Council. The new state-of-the-art campus has been planned to deliver against the needs of the local community and priority national skills needs and will include:

  • Industry-standard workshops for engineering and construction
  • Centres of excellence for engineering, construction, the built environment and sport
  • A university hub, allowing learners to study to degree level with a range of university partners on campus
  • Conference facilities, enabling the College to engage with national, regional and local businesses and provide catered conferencing events
  • An innovation and events hub, to cater for College, industry and community events
  • A multi-court sports pavilion, allowing the College to expand and diversify provision in sport and wellbeing for students and the local community
  • Year-round outdoor learning spaces throughout the campus to be accessible and used by students and locals alike

How does the project contribute to Local Economic Development: The new Fife College campus will contribute to the economy of the Region as a whole by:

  • ensuring College is capable of responding to the changing demographics of the region
  • providing education and training required at the SCQF levels identified by labour market intelligence as the ones most likely to be in demand for future jobs;
  • supporting all of the region's key employment sectors
  • providing the region with a platform to greatly enhance its capacity to deliver innovation and product development in key areas, including health and care and STEM (science, technology, engineering and mathematics)

The College has adopted the Scottish Futures Trust's TOMs (Themes, Outcomes and Measures) for managing and delivering social and economic value through the project and they expect to deliver benefits in excess of £15 million.

Sector: Justice

Project Name: HMP Highland

How does the project support the Scottish Government's Climate Change Targets: The Scottish Prison Service (SPS) will actively monitor the environmental and greenhouse gas emissions impact of the new facility. Measures are planned for the next design stage to further align HMP Highland with SG Net Zero emissions.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: SPS is working with the contractor and their design team to develop the design of the new facility to incorporate energy reducing measures, utilising a range of available low carbon energy sources and to facilitate future substitution with zero carbon energy sources.

The digital infrastructure proposed will assist SPS in advancing the digital transformation of its Estate and business and provide wider access to digital services for those in our care and their families. To enhance digital inclusion, this will include having the digital infrastructure to enable the people in our care to access digital services as they are enabled. Such services are being developed within SPS's Digital Strategy.

The replacement of the current HMP Inverness (will expand the provision of custodial services available within the local community and reduce reliance on accommodation in other (principally Central Belt) locations.

How does the project contribute to Local Economic Development: In February 2022, the Scottish Prison Service (SPS) met with Balfour Beatty, the contractor, to discuss progress on developing and enhancing the proposed Community Benefit Plan (CBP) for the design and construction of HMP Highland. A number of early engagement sessions were also held with representatives from various potential partner organisations. Additionally, Balfour Beatty provided an update to SPS on progress with how their supply chain will contribute. The following organisations were met:

  • Highland Council Employability Services
  • Highland Drug & Alcohol Partnership
  • Highland TSI (Third Sector Interface)
  • Apex Highland
  • Construction Industry Training Board
  • Inverness University of the Highlands and Islands

Further meetings are currently being scheduled for the forthcoming period.

Project Name: National Facility for Women Offenders

How does the project support the Scottish Government's Climate Change Targets: SPS will actively monitor the environmental and greenhouse gas emissions impact of the new facility. The design of the new facility incorporates low carbon energy sources (ground source heating and PV (photovoltaic) arrays) and energy use reduction measures

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The digital infrastructure proposed will assist SPS in advancing the digital transformation of its Estate and business and provide wider access to digital services for those in our care and their families. To enhance digital inclusion, this will include having the digital infrastructure to enable the people in our care to access digital services as they are enabled. Such services are being developed within SPS's Digital Strategy.

The development supports sustainable and resilient places by allowing delivery of custodial and support services at a local level, rather than reliance on remote or regional service provision, and provide access to community based work and training opportunities.

How does the project contribute to Local Economic Development: Following the easing of COVID restrictions, SPS, in conjunction with Morrison Construction, have sought to re-engage the community benefits where possible. Morrison Construction Community Benefits Team continues to liaise with SPS on a monthly basis to implement their 'pathways to employment' programme in partnership with Wise Group to facilitate the women of Cornton Vale into employment. In addition, the contractor has liaised directly with the women currently accommodated in the existing HMP Cornton Vale, to develop proposals for therapeutic gardens and landscaping which the women will themselves implement in the new establishment on completion. The contractor continues to make direct contributions to local community groups.

Project Name: Community Custodial Unit D - Dundee

How does the project support the Scottish Government's Climate Change Targets: SPS will actively monitor the environmental and greenhouse gas emissions impact of the new facility. The design of the new facility incorporates low carbon energy sources (PV (photovoltaic) arrays) and energy use reduction measures.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The digital infrastructure proposed will assist SPS in advancing the digital transformation of its Estate and business and provide wider access to digital services for those in our care and their families. To enhance digital inclusion, this will include having the digital infrastructure to enable the people in our care to access digital services as they are enabled. Such services are being developed within SPS's Digital Strategy.

The development supports sustainable and resilient places by allowing delivery of custodial and support services at a local level, rather than reliance on remote or regional service provision, and provide access to community based work and training opportunities.

How does the project contribute to Local Economic Development: Due to COVID-19 pandemic, there has been limited community engagement by the contractor throughout duration of construction. However, one aspect of project, which has been subject to continued community engagement, is the community art installation project. They have also been involved in supplying a new water tap for the local community garden and have recently been engaging with education sectors regarding work experience and placement opportunities.

Project Name: Community Custodial Unit E - Lilias Centre, Maryhill

How does the project support the Scottish Government's Climate Change Targets: SPS will actively monitor the environmental and greenhouse gas emissions impact of the new facility. The design of the new facility incorporates low carbon energy sources (PV (photovoltaic) arrays) and energy use reduction measures.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The digital infrastructure proposed will assist SPS in advancing the digital transformation of its Estate and business and provide wider access to digital services for those in our care and their families. To enhance digital inclusion, this will include having the digital infrastructure to enable the people in our care to access digital services as they are enabled. Such services are being developed within SPS's Digital Strategy.

The development supports sustainable and resilient places by allowing delivery of custodial and support services at a local level, rather than reliance on remote or regional service provision, and provide access to community based work and training opportunities.

How does the project contribute to Local Economic Development: The contractor has implemented a community engagement programme which included targets for minimum expenditure with local suppliers (circa £1.25 million), commitment to apprentice programmes (4), 'new start' employment opportunities (2) and a series of other initiatives such as work placements and industry awareness events. These obligations have been met.

Project Name: HMP Barlinnie Programme of Works

How does the project support the Scottish Government's Climate Change Targets: HMP Barlinnie Programme of Works primarily consists of internal fit out works. Nothing to report for this section.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: This programme enhances the care available and experience of those in custody within Barlinnie and reduces the issues experienced in Barlinnie due to the ageing infrastructure while its replacement, HMP Glasgow, is developed. The investment is targeted at improvements in healthcare provision and reception processes that can have a major impact on a person's initial contact with a custodial environment and subsequent engagement.

How does the project contribute to Local Economic Development: The appointed contractor has to deliver demonstrable community benefits as part of their building contract and has held workshops with a number of stakeholders and parties. The contractor has engaged with Families Outside (a National charity working with families of those in custody) to provide training in software packages for those that they work with. Further engagement is ongoing.

During Scotland Apprenticeship Week in March 2021, the contractor worked with Developing the Young Workforce and Skills Development Scotland promoting apprenticeships in construction and during Women in Construction Week promoted careers in construction for women and engaged with Job Centre Plus with on-line events. Further engagement is ongoing.

The SPS operational team at HMP Barlinnie has provided additional information to assist the contractor in making further contact with other external stakeholders, not previously identified in their benefits plan, to continue their community engagements.

Sector: Rural and Environment

Project Name: RBGE - Edinburgh Biomes

How does the project support the Scottish Government's Climate Change Targets: A core benefit of the programme will be that building and energy systems will contribute to meeting the Scottish Government targets for emissions by reduction of carbon emissions of 17% over the asset life cycle.

How does the project support the three themes of the Scottish Government's Infrastructure Investment Plan Strategic Themes: The programme will protect and enrich the National Botanical Collections, which are important for global plant conservation and maintaining the discovery science required to better understand and improve sustainability and help tackle the Biodiversity Crisis and Climate Emergency.

The RBGE Biomes will provide world-class displays and facilities that are key in supporting the public's understanding of the need to respond to the Biodiversity Crisis and Climate Emergency and raising associated national and international reputation. The outcomes will deliver economic, circular economy and societal benefit by reducing RBGE's carbon footprint and leading on carbon management and environmental public engagement projects arising from Edinburgh Biomes to encourage wider behaviour change.

Programme will provide fit-for-purpose facilities to ensure that RBGE and Scotland continues to deliver world leading, innovative and high impact plant and conservation research. - Facilities will deliver a legislatively compliant and future adaptive Plant Health Suite (PHS) that enhances and accelerates research into current and near threat plant pests and pathogens and achieves the highest possible standards of biosecurity for Scotland.

A revitalised visitor experience, increasing the diversity, number and experience of community, educational, family, and individual users through improved interpretation and more inclusive facilities. Building and energy systems that will contribute to meeting the Scottish Government targets for emissions by reduction of carbon emissions of 17% over the asset life cycle. Forecast to reduce annual energy consumption costs by £250k per annum.

How does the project contribute to Local Economic Development: The project is forecast to make a significant contribution to Scotland's green recovery. The total economic benefit of the project construction is estimated at £150 million. It will also support the growth of regional businesses, with over £50 million to be spent in local supply chain through contracts.

Forecast to create over green 100 jobs per annum, throughout construction, and support sector and locality-based employment, and skills development in collaboration with partners. Planned provision of wider employment opportunities including apprenticeships, internships, S5 and S6 school release and career placements to kick start green/urban upskilling and all associated community benefits for the duration of the project and beyond.

Contact

Email: stuart.mckeown@gov.scot

Back to top