Publication - Corporate report
Autumn Budget Revision 2024-25: supporting document
Supporting document to the Budget (Scotland) Act 2024 Amendment Regulations 2024. Provides details of Level 2 and 3 budgets.
Social Justice
Schedule 2.1 Total Changes for the Autumn Budget Revision
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Total Budget in the Budget Act | 7,537.655 | 26.359 | 7,564.014 |
| Changes Proposed | |||
| Funding Changes | -160.000 | 0.000 | -160.000 |
| Technical Adjustment | 0.076 | 0.000 | 0.076 |
| Net Whitehall Transfers | 15.029 | 0.000 | 15.029 |
| Net Transfers within Scottish Block | -137.705 | 40.000 | -97.705 |
| Total changes proposed | -282.600 | 40.000 | -242.600 |
| Proposed Budget following Autumn Budget Revision | 7,255.055 | 66.359 | 7,321.414 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Expenditure Limit: | |||
| Third Sector | 14.721 | 0.000 | 14.721 |
| Housing and Building Standards | 492.978 | -5.100 | 487.878 |
| Cladding | 41.309 | 0.000 | 41.309 |
| Tackling Child Poverty and Social Justice | 50.023 | 0.000 | 50.023 |
| Equalities, Inclusion and Human Rights | 52.781 | 0.000 | 52.781 |
| Transfer of the Management of Development Funding | 92.245 | 0.000 | 92.245 |
| Social Security | 473.869 | 71.459 | 545.328 |
| Social Security Assistance | 5,985.380 | 0.000 | 5,985.380 |
| Ukrainian Resettlement | 51.749 | 0.000 | 51.749 |
| Migration Strategy | 0.000 | 0.000 | 0.000 |
| Total Expenditure Limit | 7,255.055 | 66.359 | 7,321.414 |
| UK Funded AME: | |||
| Social Security (AME) | 0.000 | 0.000 | 0.000 |
| Total UK Funded AME | 0.000 | 0.000 | 0.000 |
| Other Expenditure: | |||
| Total Other Expenditure | 0.000 | 0.000 | 0.000 |
| Total Budget | 7,255.055 | 66.359 | 7,321.414 |
| Total Limit on Income (accruing resources) | 90.000 |
Schedule 3.1 Third Sector
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 21.077 | 0.000 | 21.077 |
| Proposed changes | -6.356 | 0.000 | -6.356 |
| ABR Proposed Budget | 14.721 | 0.000 | 14.721 |
| Summary of proposed changes | |||
| Funding to Growth Accelerators required due to the movement of the Enterprising Third Sector team from DG Communities to DG Economy. | -6.269 | 0.000 | -6.269 |
| Miscellaneous Minor Transfers | -0.087 | 0.000 | -0.087 |
| -6.356 | 0.000 | -6.356 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 14.721 | 0.000 | 14.721 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 14.721 | 0.000 | 14.721 | |
| Budget Analysis | |||
| Third Sector | 14.721 | 0.000 | 14.721 |
| Net Expenditure | 14.721 | 0.000 | 14.721 |
Schedule 3.2 Housing & Building Standards
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 578.339 | -45.100 | 533.239 |
| Proposed changes | -85.361 | 40.000 | -45.361 |
| ABR Proposed Budget | 492.978 | -5.100 | 487.878 |
| Summary of proposed changes | |||
| From General Revenue Grant to cover Building Sandards Fees | 2.100 | 0.000 | 2.100 |
| Funding to Local Government for Discretionary Housing Payments | -76.175 | 0.000 | -76.175 |
| Funding to General Revenue Grant to implement their Rapid Rehousing Transition Plan to reduce homelessness. | -8.000 | 0.000 | -8.000 |
| Funding to Scottish Courts and Tribunal Service for Housing & Property Chamber - Private Rented Sector | -3.170 | 0.000 | -3.170 |
| Funding from Energy Efficiency and Decarbonisation for the installation of zero emission heating systems as part of the affordable homes programme | 0.000 | 40.000 | 40.000 |
| Miscellaneous Minor Transfers | -0.116 | 0.000 | -0.116 |
| -85.361 | 40.000 | -45.361 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 492.978 | -5.100 | 487.878 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 492.978 | -5.100 | 487.878 | |
| Budget Analysis | |||
| Fuel Poverty/Energy Efficiency | 1.496 | 0.000 | 1.496 |
| Housing Support | 65.966 | 0.000 | 65.966 |
| Building Standards | 4.540 | 0.000 | 4.540 |
| More Homes | 420.976 | -5.100 | 415.876 |
| Net Expenditure | 492.978 | -5.100 | 487.878 |
Schedule 3.3 Cladding
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 41.309 | 0.000 | 41.309 |
| Proposed changes | 0.000 | 0.000 | 0.000 |
| ABR Proposed Budget | 41.309 | 0.000 | 41.309 |
| Summary of proposed changes | |||
| 0.000 | 0.000 | 0.000 | |
| 0.000 | 0.000 | 0.000 | |
| 0.000 | 0.000 | 0.000 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 41.309 | 0.000 | 41.309 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 41.309 | 0.000 | 41.309 | |
| Budget Analysis | |||
| Cladding | 41.309 | 0.000 | 41.309 |
| Net Expenditure | 41.309 | 0.000 | 41.309 |
Schedule 3.4 Tackling Child Poverty and Social Justice
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 43.019 | 0.000 | 43.019 |
| Proposed changes | 7.004 | 0.000 | 7.004 |
| ABR Proposed Budget | 50.023 | 0.000 | 50.023 |
| Summary of proposed changes | |||
| Funding from Whitehall for Debt Advice Levy | 7.324 | 0.000 | 7.324 |
| Miscellaneous Minor Transfers | -0.320 | 0.000 | -0.320 |
| 7.004 | 0.000 | 7.004 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 50.023 | 0.000 | 50.023 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 50.023 | 0.000 | 50.023 | |
| Budget Analysis | |||
| Communities Analysis | 6.080 | 0.000 | 6.080 |
| Social Justice | 43.943 | 0.000 | 43.943 |
| Net Expenditure | 50.023 | 0.000 | 50.023 |
Schedule 3.5 SJ Central Government Grants to Local Authorities
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 92.245 | 0.000 | 92.245 |
| Proposed changes | 0.000 | 0.000 | 0.000 |
| ABR Proposed Budget | 92.245 | 0.000 | 92.245 |
| Summary of proposed changes | |||
| 0.000 | 0.000 | 0.000 | |
| 0.000 | 0.000 | 0.000 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 92.245 | 0.000 | 92.245 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 92.245 | 0.000 | 92.245 | |
| Budget Analysis | |||
| Transfer of the Management of Development Funding | 92.245 | 0.000 | 92.245 |
| Net Expenditure | 92.245 | 0.000 | 92.245 |
Schedule 3.6 Social Security
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 496.111 | 71.459 | 567.570 |
| Proposed changes | -22.242 | 0.000 | -22.242 |
| ABR Proposed Budget | 473.869 | 71.459 | 545.328 |
| Summary of proposed changes | |||
| Reduction in Social Security Scotland budget for staffing savings outlined in Fiscal Statement | -12.000 | 0.000 | -12.000 |
| Transfer to Local Government Finance to supply support to local authorities to provide the Scottish Welfare Fund | -5.373 | 0.000 | -5.373 |
| Funding to General Revenue Grant regarding Disability Benefit applications | -3.500 | 0.000 | -3.500 |
| First-tier Tribunal for Scotland Social Security Chamber funding | -1.634 | 0.000 | -1.634 |
| Miscellaneous Minor Transfers | 0.265 | 0.000 | 0.265 |
| -22.242 | 0.000 | -22.242 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 473.869 | 71.459 | 545.328 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 473.869 | 71.459 | 545.328 | |
| Budget Analysis | |||
| Scottish Welfare Fund Administration | 0.100 | 0.000 | 0.100 |
| Social Security Advice Policy and Programme Costs | 159.941 | 66.290 | 226.231 |
| Social Security (AME) | 0.000 | 0.000 | 0.000 |
| Social Security Scotland | 313.828 | 5.169 | 318.997 |
| Net Expenditure | 473.869 | 71.459 | 545.328 |
Schedule 3.7 Social Security Assistance
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 6,168.880 | 0.000 | 6,168.880 |
| Proposed changes | -183.500 | 0.000 | -183.500 |
| ABR Proposed Budget | 5,985.380 | 0.000 | 5,985.380 |
| Summary of proposed changes | |||
| Reduction in Pension Age Winter Heating Payment forecast following change to eligiblity | -148.000 | 0.000 | 0.000 |
| Transfer to Local Government Finance to supply support to local authorities to provide the Scottish Welfare Fund | -35.500 | 0.000 | -35.500 |
| -183.500 | 0.000 | -35.500 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 5,985.380 | 0.000 | 5,985.380 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 5,985.380 | 0.000 | 5,985.380 | |
| Budget Analysis | |||
| Adult Disability Payment | 3,226.400 | 0.000 | 3,226.400 |
| Attendance Allowance | 754.900 | 0.000 | 754.900 |
| Scottish Child Payment | 457.340 | 0.000 | 457.340 |
| Child Disability Assistance (DLA Child and DACYP) | 450.100 | 0.000 | 450.100 |
| Disability Living Allowance (Adult) | 420.000 | 0.000 | 420.000 |
| Carer's Allowance | 411.700 | 0.000 | 411.700 |
| Pension Age Winter Heating Payment | 32.000 | 0.000 | 32.000 |
| Industrial Injuries Disablement Scheme | 86.600 | 0.000 | 86.600 |
| Carer's Allowance Supplement | 55.100 | 0.000 | 55.100 |
| Scottish Welfare Fund | 0.000 | 0.000 | 0.000 |
| Low Income Winter Heating Assitance | 24.400 | 0.000 | 24.400 |
| Best Start Grant | 21.300 | 0.000 | 21.300 |
| Best Start Food Grant | 18.100 | 0.000 | 18.100 |
| Funeral Support Payment | 12.200 | 0.000 | 12.200 |
| Child Winter Heating Allowance | 8.700 | 0.000 | 8.700 |
| Severe Disablement Allowance | 5.140 | 0.000 | 5.140 |
| Young Carer Grant | 1.000 | 0.000 | 1.000 |
| Job Start Payment | 0.400 | 0.000 | 0.400 |
| Net Expenditure | 5,985.380 | 0.000 | 5,985.380 |
Schedule 3.8 Equalities, Inclusion and Human Rights
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 51.856 | 0.000 | 51.856 |
| Proposed changes | 0.925 | 0.000 | 0.925 |
| ABR Proposed Budget | 52.781 | 0.000 | 52.781 |
| Summary of proposed changes | |||
| Miscellaneous minor transfers | 0.925 | 0.000 | 0.925 |
| 0.925 | 0.000 | 0.925 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 52.781 | 0.000 | 52.781 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 52.781 | 0.000 | 52.781 | |
| Budget Analysis | |||
| Equalities, Inclusion and Human Rights | 52.781 | 0.000 | 52.781 |
| Net Expenditure | 52.781 | 0.000 | 52.781 |
Schedule 3.9 Ukrainian Resettlement
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 44.819 | 0.000 | 44.819 |
| Proposed changes | 6.930 | 0.000 | 6.930 |
| ABR Proposed Budget | 51.749 | 0.000 | 51.749 |
| Summary of proposed changes | |||
| Funding from Whitehall in respect of Ukrainian refugee Thank You payments | 7.705 | 0.000 | 7.705 |
| Miscellaneous Minor Transfers | -0.775 | 0.000 | -0.775 |
| 6.930 | 0.000 | 6.930 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 51.749 | 0.000 | 51.749 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 51.749 | 0.000 | 51.749 | |
| Budget Analysis | |||
| Ukrainian Resettlement | 51.749 | 0.000 | 51.749 |
| Net Expenditure | 51.749 | 0.000 | 51.749 |
Schedule 3.10 Migration Strategy
Details of Proposed Budget
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Original Budget | 0.000 | 0.000 | 0.000 |
| Proposed changes | 0.000 | 0.000 | 0.000 |
| ABR Proposed Budget | 0.000 | 0.000 | 0.000 |
| Summary of proposed changes | |||
| 0.000 | 0.000 | 0.000 | |
| 0.000 | 0.000 | 0.000 |
| Operating £m | Capital £m | Total £m | |
|---|---|---|---|
| Gross Expenditure | 0.000 | 0.000 | 0.000 |
| Less: Retained Income | 0.000 | 0.000 | 0.000 |
| Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
| 0.000 | 0.000 | 0.000 | |
| Budget Analysis | |||
| Migration Strategy | 0.000 | 0.000 | 0.000 |
| Net Expenditure | 0.000 | 0.000 | 0.000 |