Information

Scottish 4G infill programme: progress update

Progress made on the mast sites currently in the Scottish 4G Infill programme and information about how mast sites progress to delivery.


Find out more about the Scottish 4G Infill programme using the following links:

Progress updates on mast sites

The Scottish Government’s Scottish 4G Infill Programme (S4GI) is a £28.75 million initiative delivering 4G infrastructure and services in up to 55 mobile “notspots” in rural and remote parts of Scotland. S4GI is being delivered in partnership with WHP Telecoms Ltd and the Scottish Futures Trust. S4GI is part-funded by the European Regional Development Fund (ERDF) to support activity in the Highlands and Islands.

We are pleased to report the following progress on the mast sites currently in the S4GI programme.

Live sites

Position on the site map Site location Progress update
1 Collieston 4G services are now available from EE
2 Blairmore 4G services are now available from EE
3 Manish 4G services are now available from EE
4 Ettrick 4G services are now available from Vodafone and O2
5 Lemreway 4G services are now available from EE
6 Strathconon 4G services are now available from EE
7 New Luce 4G services are now availalbe from Vodafone and EE
8 Tarskavaig 4G services are now available from EE
9 Applecross 4G services are now available from EE
10 Bunessan 4G services are now available from EE
11 Traquair 4G services are now available from EE
12 Glenbarr 4G services are now available from EE
13 Ae 4G services are now available from EE
14 Glenborrodale (formerly referred to as Glencripesdale) 4G services are now available from EE
15 Polbain 4G services are now available from EE
16 Killilan 4G services are now available from EE
17 Chapeltown 4G services are now available from EE
18 Reawick (formerly referred to as Selivoe) 4G services are now available from EE
19 Whitropefoot 4G services are now available from EE
20 Ranish 4G services are now available from EE
21 Littlemill 4G services are now available from EE
22 Loch Head 4G services are now available from EE
23 Auchenhessnane 4G services are now available from EE
24 Bogton Turriff 4G services are now available from EE.
25 Cairngarroch 4G services are now available from EE
33 Baymore 4G services are now available from EE
34 Deerness 4G services are now available from EE
35 Skerray 4G services are now available from EE
36  Burray 4G services are now available from EE


Sites currently at the build stage

Position on the site map Site location Progress update
26 Brecklate Construction is completed. 4G services from EE are expected to be available later in 2022
27 Elgol Construction is completed with power and transmission connection ongoing, and EE has agreed to use this site. Once the transmission connection is completed, we will be able to forecast service availability
28 Inverchoran Construction is completed. 4G services from EE are expected to be available later in 2022
29 Rackwick Construction is completed with transmission connection ongoing, and EE has agreed to use this site. Once the transmission connection is completed, we will be able to forecast service availability
30 Ardlussa Construction is complete with power and fibre connections ongoing. Once the transmission connection is completed, we will be able to forecast service availability
31 Craighouse Construction is complete. 4G services from EE are expected to be available later in 2022
32 Lochbuie Construction is complete with power complete and fibre connections ongoing. Once the transmission connection is completed, we will be able to forecast service availability
35 Skerray

Construction is completed with power connected and fibre connection ongoing. 4G services from EE are expected to be available spring 2022

38 Bruray Planning permission and landowner consents are in place, and EE have agreed to use this site. Construction work is underway
40 Garvald Construction is completed with fibre completed and power connection ongoing. Vodafone and O2 have agreed to use this site and 4G services expected to be available later in 2022
41 Carrine Construction is completed. Vodafone and O2 have agreed to use this site and 4G services expected to be available later in 2022
42 Ham Planning permission and landowner consents are in place, and EE have agreed to use this site. Construction work is underway
43 Balmacara Planning permission and landowner consents are in place, and Vodafone and O2 have agreed to use this site. Construction work is underway
44 Deanburnhaugh Construction is complete with power complete with transmission connection ongoing.  EE has agreed to use this site and 4G services are expected to be available later in 2022
45 Stronachlachlar Construction is complete with power complete and transmission connection ongoing. EE have agreed to use this site, once the transmission connection is completed, we will be able to forecast service availability
50 Kenmore Construction is complete with power and fibre connections ongoing. EE have agreed to use this site and 4G services expected to be available later in 2022.
52 Clova Planning permission and landowner consents are in place, and EE have agreed to use this site. Construction work is underway
53 Ellemford Construction is complete. EE has agreed to use this site and 4G services expected to be available later in 2022.
55 Stronsay Construction is complete with power complete and transmittion connection ongoing. Once the transmission connection is completed, we will be able to forecast service availability
56 Condie Construction is complete with power complete and fibre connections ongoing. EE has agreed to use this site
58 Sourhope Construction is complete with power and transmission connection ongoing. Once the transmission connection is completed, we will be able to forecast service availability
59 Cawdor Planning permission and landowner consents are in place, and EE have agreed to use this site. Construction work is underway


Sites at the pre-build stage

Position on sites map Site location Progress update
37 Crinan Planning permission and landowner consents are in place, and 3UK have agreed to use this site, build to be scheduled
39 Kilchoman Planning Permission and Landowner consents are in place, anchor operator awaited
46 The Craigs Planning Permission and Landowner consents are ongoing
47 Corrie Common Planning permission and landowner consents are in place, and EE have agreed to use this site, build to be scheduled
48 Kinlochard Planning Permission and Landowner consents are in place, anchor operator awaited
49 Inverie (formerly referred to as Mallaig) Planning permission and landowner consents are ongoing
51 Achosnich Planning permission and landowner consents are in place, and EE have agreed to use this site, build to be scheduled.
57  Druimindarroch Planning Permission and Landowner consents are ongoing
60 Corrie Common Planning permission and landowner consents are in place, and EE have agreed to use this site, build to be scheduled


Removals from the S4GI Programme

Regrettably, we have no option but to remove the following previously proposed candidate sites from the Scottish 4G Infill Programme. With the following exceptions, this is because no mobile network operators have committed to using them:

* Carrick Castle, Berneray Harbour: removed as commercial services by EE were found to be available in the area.

** Applecross Forest: removed as another mast which is expected to provide 4G services has recently been constructed in the area.

† Pennan: in addition to no MNO interest, planning permission was refused following local opposition.

‡ Muircroft, Cullipool, Charlestown: removed as EE is now planning to deliver 4G services to these areas on a commercial basis.

Carrick Castle*

Eriskay

Pennan

Strathyre

Outertown

Watten

Hoy

Clachan Seil

Arnisdale

Cuidrach

Drummuir

Charlestown‡

Bettyhill

Muircroft‡

Garvald (Mendick)

Cullipool‡

Blackhill

Berneray Harbour*

Applecross Forest**  

How mast sites progress to delivery

Building a mobile mast from initial site selection to the final switch-on is a lengthy process involving several important stages. These can be complex and take time to achieve. 

When a mast site is included in the programme, WHP Telecoms Ltd – the Scottish Government’s Infrastructure Provider – begins site acquisition activity in order to achieve each of three fundamental consents to progress delivery of the mast.

These are: 

  • agreed terms with a landowner
  • achievement of planning permission from the local planning authority
  • commitment from at least one mobile network operator (EE, O2, Three, Vodafone) to providing 4G mobile services from that site

WHP Telecoms Ltd. is currently involved in intensive discussions with potential landlords, planning authorities, communities and mobile network operators to achieve these three consents.

During this process the exact site location is determined. This can differ from the indicative locations denoted by national grid references previously published by the Scottish Government.

All three of these consents must be in place before any physical mast build will take place.  At this stage, we will be in a position to give an indicative timeline for delivery of mobile services.

If all three consents cannot be achieved, then regrettably that site will not be able to progress. However, we will keep the site under review should circumstances change.

Mobile masts also require a power supply and backhaul (ideally using fibre or alternatively a microwave connection back to national telecoms networks). Both must be at a cost that is affordable within the overall programme budget. In parallel with the site acquisition process, WHP Telecoms Ltd. is currently in active discussion with power and backhaul suppliers to achieve this.  Costs could be high if the local topography is challenging or if the site is distant from the nearest fibre route or electricity supply.

Once all of the above elements are in place, the mast will progress to the construction phase. Once completed, the mobile network operator can complete the process by installing their equipment and switching on the service.  

The programme will provide regular progress updates on this website with clear reasons should any masts be unable to progress.

Map of programme sites

Contact

Email: digitalconnectivity@gov.scot

Post:
Scottish Government
Connectivity, Economy and Participation Division
Atlantic Quay
Glasgow
G2 8LU

Telephone: 0300 244 4000

Back to top