Rejected planning applications involving renewable energy projects: EIR release
- Published
- 2 November 2023
- Topic
- Public sector
- FOI reference
- 202300358947
- Date received
- 25 May 2023
- Date responded
- 20 June 2023
Information request and response under the Environmental Information (Scotland) Regulations 2004
Information requested
You asked for -
"How many rejected planning applications involving renewable energy projects have the Scottish Government planners overturned in 2021 and 2022? Can you please list them or direct me to where I can find this information."
As the information you have requested is 'environmental information' for the purposes of the Environmental Information (Scotland) Regulations 2004 (EIRs), we are required to deal with your request under those Regulations. We are applying the exemption at section 39(2) of the Freedom of Information (Scotland) Act 2002 (FOISA), so that we do not also have to deal with your request under FOISA.
This exemption is subject to the 'public interest test'. Therefore, taking account of all the circumstances of this case, we have considered if the public interest in disclosing the information outweighs the public interest in applying the exemption. We have found that, on balance, the public interest lies in favour of upholding the exemption, because there is no public interest in dealing with the same request under two different regimes. This is essentially a technical point and has no material effect on the outcome of your request.
Response
I enclose a list of the information available on our internal appeals database in response to your request above.
Rejected Planning applications, involving renewable energy overturned -
|
|
|
|
|
case reference |
characteristic |
date decision issued |
decision description |
|
PPA-110-2401 |
Wind turbine (single) |
14/01/2021 |
Appeal Allowed |
|
PPA-110-2406 |
Wind turbine (single) |
06/09/2021 |
Appeal Allowed |
|
PPA-110-2407 |
Wind Farm (two or more turbines) |
21/07/2021 |
Appeal Allowed |
|
PPA-110-2407 |
Hydro/Solar Power |
21/07/2021 |
Appeal Allowed |
|
PPA-270-2242 |
Wind Farm (two or more turbines) |
28/07/2021 |
Appeal Allowed |
|
PPA-270-2250 |
Wind Farm (two or more turbines) |
07/01/2022 |
Appeal Allowed |
|
PPA-270-2256 |
Wind Farm (two or more turbines) |
23/08/2022 |
Appeal Allowed |
|
PPA-110-2420 |
Wind Farm (two or more turbines) |
29/09/2022 |
Appeal Allowed |
|
PPA-300-2066 |
Wind Farm (two or more turbines) |
26/09/2022 |
Appeal Allowed |
|
PPA-330-2029 |
Wind Farm (two or more turbines) |
11/04/2022 |
Appeal Allowed |
|
PPA-130-2084 |
Wind Farm (two or more turbines) |
07/11/2022 |
Appeal Allowed |
|
Total |
|
|
11 |
Further information including the final decision regarding these cases above can be found on our website - Scottish Government - DPEA - Case List (scotland.gov.uk) by searching using the case reference number.
About FOI
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.
Contact
Please quote the FOI reference
Central Enquiry Unit
Email: ceu@gov.scot
Phone: 0300 244 4000
The Scottish Government
St Andrews House
Regent Road
Edinburgh
EH1 3DG