Planning decision: installation of temporary viewing platform at Torry Battery, Aberdeen

Planning proposal relating to installation of temporary viewing platform, supporting foundations, soakaway pit, decking and walkway at Torry Battery, 130M ESE of Old South Breakwater (ref. SMC-ABD-001). This case is closed.

This document is part of a collection


Status of case: closed
Action: cleared back to the planning authority for their own determination
Action date: 02/04/2019

Scottish Government case reference number: SMC-ABD-001
Planning authority: Historic Environment Scotland
Planning authority case reference number: AMH/9215/1/1

Scottish Ministers may intervene in determining a planning proposal, whether an application or an appeal, where it is felt there is a national interest in doing so. We make all correspondence between ourselves, planning authorities and Historic Environment Scotland relating to each case's progress available to the public. 

The attached documents relate to a planning permission application for installation of temporary viewing platform, supporting foundations, soakaway pit, decking and walkway at Torry Battery, 130M ESE of Old South Breakwater, Aberdeen:

  • letter commencing consideration period
  • Planning and Architecture Division assessment report
  • clearance letter

More information

Planning Circular 3 2009: notification of planning applications provides context to the above proposal

 

SMC-ABD-001 - letter commencing consideration period
SMC-ABD-001: clearance letter

Contact

Email: planning.decisions@gov.scot

Telephone: 0131 244 7073

Post: 

Area 2-F (South)
Planning and Architecture Division
The Scottish Government
Victoria Quay
Edinburgh
EH6 6QQ