Road works undertaken on the A83 at Strone Point: EIR release
- Published
- 12 November 2018
- Topic
- Public sector, Transport
Information request and response under the Environmental Information (Scotland) Regulations 2004.
Date received: 18 October 2018
Date responded: 12 November 2018
1. Details of all road works and the work being undertaken on the A83 at Strone Point, approximately 3 km north east of Inveraray between 01/06/2018 and 01/08/2018.
2. Details of the completion date of any road works being undertaken on the A83 at Strone Point, approximately 3 km north east of Inveraray between 01/06/2018 and 01/08/2018.
3. Details of any risk assessments completed in anticipation of any road works being undertaken on the A83 at Strone Point, approximately 3 km north east of Inveraray between 01/06/2018 and 1/08/2018
4. Details of any contractors carrying out works on the A83 at Strone Point, approximately 3 km north east of Inveraray between 01/06/2018 and 01/08/2018.
This exemption is subject to the ‘public interest test’. Therefore, taking account of all the circumstances of this case, we have considered if the public interest in disclosing the information outweighs the public interest in applying the exemption. We have found that, on balance, the public interest lies in favour of upholding the exemption, because there is no public interest in dealing with the same request under two different regimes. This is essentially a technical point and has no material effect on the outcome of your request.
I have numbered our response for ease of reference.
1. The works, 3 km north east of Inveraray between 01/06/2018 and 01/08/2018 was the A83 Strone Point Realignment Project. Please refer to Annex A which contains details of the work undertaken.
2. The completion date of the works was 11 July 2018.
3. Please refer to Annex B which is the Risk Assessments completed for these works. An exception under regulation 11(2) of the EIRs (personal information) applies to some of the information requested because it is personal data of a third party and disclosing it would contravene the data protection principles in Article 5(1) of the General Data Protection Regulation and in section 34(1) of the Data Protection Act 2018. This exception is not subject to the ‘public interest test’, so we are not required to consider if the public interest in disclosing the information outweighs the public interest in applying the exception.
4. The table below contains details of the contractors involved with these works.
Main Contractor |
John Paul Construction
|
Contractors |
FBM Contracts – Groundworks |
|
Cooper Contracts – Site Clearance and Earthworks |
|
Highland Fencing and Barrier Contractors Ltd – Vehicle Restraint Systems |
|
Geo-Rope – Slope Stabilisation |
|
CJT Utilities – Utilities |
|
Aggregate Industries – Pavement Construction |
|
Markon – Road Markings and High Friction Surfacing |
|
Argyll & Bute Environmental Ltd (ABEL) – Drainage Testing and Investigation |
|
Dee Organ (Mallatite) – Signage Installation |
|
Ensol Retaining Structures – Retaining Wall Construction |
|
Ashlea Ltd – Hydroseed |
|
Highway Barrier Solutions (HBS) – Traffic Management |
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses
- File type
- 30 page PDF
- File size
- 2.0 MB
- File type
- File size
- 3.1 MB
- File type
- File size
- 2.7 MB
- File type
- File size
- 741.7 kB
- File type
- 5 page PDF
- File size
- 167.3 kB
Contact
Please quote the FOI reference
Central Enquiry Unit
Email: ceu@gov.scot
Phone: 0300 244 4000
The Scottish Government
St Andrew's House
Regent Road
Edinburgh
EH1 3DG
There is a problem
Thanks for your feedback