The quarterly update of Scottish Welfare Fund Statistics for October to December 2025. This includes quarterly statistics on Community Care Grants and Crisis Grants from 2021 onwards.


During October to December 2025, local authorities processed 86% of Community Care Grant applications within the target time of 15 working days (Table 8, Chart 4), and processed 98% of Crisis Grant applications within the target time of the end of the next working day (Table 10, Chart 5).

 

Four local authorities processed fewer than 80% of Community Care Grant applications on time: Glasgow (47%), Aberdeen (58%), Angus (74%) and Na-h Eileanan Siar (75%) (Table 9), and one processed fewer than 90% of Crisis Grant applications on time: Shetland (78%) (Table 11).

 

It is possible that cases are currently missing from the dataset used to produce this publication due to delays in processing or late returns, or due to cases being awarded in principle or ‘pending’ on local authority systems. It is therefore possible that estimates of the proportion processed within target times could change for the latest quarter in subsequent publications.
 

Chart 4: Initial Processing Times for Community Care Grants – Quarterly
This chart shows time series of the proportion of CCG applications within the processing time target per quarter since April 2021.

SWF Chart 4

Chart 5: Initial Processing Times for Crisis Grants – Quarterly
This chart shows time series of the proportion of CCG applications within the processing time target per quarter since April 2021.

SWF Chart 5