As at 30 September 2025, the Cladding Remediation Programme had been informed that 16 Single Building Assessments (SBAs), based on the specification published in June 2024, had been completed. This includes the high-priority SBAs that the Scottish Government commissioned for buildings that were identified as part of the pilot programme.

As at 30 September 2025, the Scottish Government Cladding Remediation Programme were not aware of any other SBAs that were yet underway but had not been completed.

Figure 4. As at 30 September 2025, SBAs had been completed in three local authority areas

The number of SBAs completed by local authority area

A bar chart with dark blue bars showing the number of completed SBAs by local authority area. Of the 16 completed SBAs, nine were carried out in Glasgow City, six were in City of Edinburgh and one was in Aberdeen City

The largest number of completed SBAs related to buildings in Glasgow City local authority area. There were also SBAs completed for buildings in the City of Edinburgh and Aberdeen City.