Planning performance statistics: quarterly reports - April to September 2019-2020
Summary statistics on planning decision-making and timescales for April to September 2019.
This document is part of a collection
4. Processing Agreements
Some local authorities use processing agreements where the developer and the local authority agree on timescales for decisions. Applications subject to a processing agreement are not included in average decision time calculations and are reported separately.
In the first six months of 2019/20 there were 1,219 applications decided that had processing agreements, 134 fewer than in the same period in the previous year.
In quarter one 6.8% of all applications (606 of 8,905) had processing agreements, in quarter two this increased to 6.9% (613 of 8,891) of all applications having a processing agreement.
Chart 19: Proportion of applications with Processing Agreements
Table 1: Processing Agreements, 2019/20, Quarter 1 and 2
Quarter 1 | Quarter 2 | |||
---|---|---|---|---|
Category of development | Number of Decisions | % Within Agreed Timescales | Number of Decisions | % Within Agreed Timescales |
Major Applications | 27 | 59.3% | 30 | 70.0% |
Local Applications | 494 | 81.4% | 487 | 78.6% |
EIA Developments | 0 | - | 0 | - |
Other Consents | 85 | 68.2% | 96 | 72.9% |
Total | 606 | 78.5% | 613 | 77.3% |