Victoria Quay swimming pool maintenance cost: FOI release

Information request and response under the Freedom of Information (Scotland) Act 2002


Information requested

You asked for the cost of maintaining the swimming pool at the Scottish Government’s Victoria Quay offices in the financial years 2020/21, 2021/22, 2022/23, 2023/24 and 2024/25. You also asked for a breakdown of all costs that have gone towards the pool in any of these calendar years, including staffing costs while it has been closed. You also asked for any projected costs to maintain the swimming pool in the current financial year 2025/26.

Response

Victoria Quay - Swimming Pool Maintenance Costs from Financial year 2020/21 through to 2025/26:

Financial Year

Maintenance Costs

2020/21

£ 30,345

2021/22

£ 26,945

2022/23

£ 39,039

2023/24

£ 0

2024/25

£ 0

2025/26

£ 0

These costs relate to planned preventative maintenance. The costs for Financial Year 2022/23 include decommissioning costs (£20,862). There are no staff costs associated with the swimming pool maintenance.

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at https://www.gov.scot/foi-responses.

Contact

Please quote the FOI reference
Central Correspondence Unit
Email: contactus@gov.scot
Phone: 0300 244 4000

The Scottish Government
St Andrew's House
Regent Road
Edinburgh
EH1 3DG

Back to top