R100 scheme: FOI release
- Published
- 5 January 2023
- Directorate
- Digital Directorate
- Topic
- Public sector
- FOI reference
- FOI/202200332531
- Date received
- 1 December 2022
- Date responded
- 28 December 2022
Information request and response under the Freedom of Information (Scotland) Act 2002.
Information requested
Information regarding the Reaching 100% (R100) programme:
1. How many premises have so far been connected through the R100 broadband scheme broken down by north, south and central lot please?
2. For the north lot, could this be broken down by constituency please?
3. Please could you tell me the estimated number of properties which are expected to be connected when each lot is completed?
Response
1. How many premises have so far been connected through the R100 broadband scheme broken down by north, south and central lot please?
The below table shows the number of premises connected in each of the three regional lots (Lot 1 North, Lot 2 Central, and Lot 3 South). As requested in follow up correspondence, figures show premises connected via R100 contract build and R100 Scottish Broadband Voucher Scheme (R100 SBVS). Please note that R100 contract build and R100 SBVS figures are accurate as at 30/11/2022.
|
Number of premises |
|
|
R100 Contract |
R100 SBVS |
Lot 1 (North) |
3,650 |
1,556 |
Lot 2 (Central) |
5,761 |
699 |
Lot 3 (South) |
5,738 |
468 |
2. For the north lot, could this be broken down by constituency please?
The below table shows the number of premises connected via R100 contract build and R100 SBVS for the North Lot, broken down by Scottish Parliament constituency – as requested in follow up correspondence.
As above, R100 contract build and R100 SBVS figures are accurate as at 30/11/2022.
|
orth Contract |
R100 S S |
|
Aberdeen Central |
0 |
0 |
|
Aberdeen Donside |
86 |
2 |
|
Aberdeen South and North Kincardine |
432 |
29 |
|
Aberdeenshire East |
328 |
190 |
|
Aberdeenshire West |
81 |
248 |
|
Angus North and Mearns |
308 |
159 |
|
Angus South |
0 |
67 |
|
Argyll and Bute |
638 |
77 |
|
Banffshire and Buchan Coast |
0 |
112 |
|
Caithness, Sutherland and Ross |
1016 |
104 |
|
Dundee City East |
0 |
1 |
|
Dundee City West |
0 |
12 |
|
Inverness and Nairn |
142 |
19 |
|
Moray |
0 |
152 |
|
Na h-Eileanan an Iar |
0 |
0 |
|
Orkney Islands |
41 |
41 |
|
Perthshire North |
106 |
105 |
|
Shetland Islands |
323 |
0 |
|
Skye, Lochaber and Badenoch |
149 |
238 |
|
Total |
3,650 |
1,556 |
3. Please could you tell me the estimated number of properties which are expected to be connected when each lot is completed?
The below table shows the number of premises contracted for delivery in each of the three regional lots (Lot 1 North, Lot 2 Central, and Lot 3 South). Please note these figures relate to the number of premises contracted for connection via R100 contracts build only. Figures for R100 SBVS cannot be provided because, as it is a demand-led scheme, the Scottish Government does not hold data on the number of premises that will secure a future connection over the lifetime of the R100 programme.
These figures are accurate as at 15/12/2022.
|
Number of premises contracted for delivery | |
Lot 1 (North) |
60,764 |
|
Lot 2 (Central) |
32,216 |
|
Lot 3 (South) |
21,889 |
About FOI
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.
Contact
Please quote the FOI reference