A9 dualling Dalraddy-Kincraig Cycle/Accessibility Audit: EIR release

Information request and response under the Environmental Information (Scotland) Regulations 2004.


Information requested

Could you forward me a copy of the Safety Audit and associated independent audit relating to the pathway please.

Response

Please find attached a copy of the Stage 3 Cycle/Accessibility Audit.

Personal information contained within this report has been redacted which is explained below.

An exception under regulation 11(2) of the EIRs (personal information) applies to some of the information requested because it is personal data of a third party and disclosing it would contravene the data protection principles in Article 5(1) of the General Data Protection Regulation and in section 34(1) of the Data Protection Act 2018. This exception is not subject to the ‘public interest test’, so we are not required to consider if the public interest in disclosing the information outweighs the public interest in applying the exception.

Stage 3 Cycle/Accessibility

The Stage 3 Cycle/Accessibility Audit has been carried out in accordance with the requirements of ‘Cycling by Design 2010’.

The Stage 3 Cycle/Accessibility Audit raised a total of twenty four “Problems”. Of these, twenty have been resolved by the contractor undertaking completion works, one is outstanding and works to resolve this is due to be completed in summer 2019, and three have been resolved through the Designer’s response to the Audit. For information I have provided a summary of the Designer’s response and the works due to be complete below.

3.1 – The Designer has responded: Provision of signage is out with the remit of this scheme.
3.13 – The Designer has responded: The junction crossing has been located away from the A9 carriageway to ensure both motorists and cyclists have sufficient visibility when approaching the crossing point. The give way markings on approach to the junction highlight to cyclists the need to slow down and give way. This will allow cyclists to position themselves to cross the junction safely.
3.24 – The Designer has responded: Physical constraints dictated the line of the NMU through this location. As NMUs have to slow down and open the gates this is not considered a hazard.
3.18 – The Contractor has confirmed that works to resolve this are due to be complete in summer 2019.

I hope the above information and enclosed cycle/accessibility audit is helpful.

About FOI
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

FOI-19-01671 - Information Released

Contact

Please quote the FOI reference
Central Enquiry Unit
Email: ceu@gov.scot
Phone: 0300 244 4000

The Scottish Government
St Andrews House
Regent Road
Edinburgh
EH1 3DG

Back to top