Scottish Budget 2023-2024: final outturn report

A statement of final outturn for the financial year 2023 to 2024 against the statutory limits authorised by the Scottish Parliament through the appropriate legislative processes.


Final Outturn – HM Treasury Controls

14. The final 2023-24 fiscal outturn confirmed with HM Treasury in December was £48.9 billion against a budget of £49.3 billion, resulting in an underspend of £412 million. This is just under 1% of the total budget (Table 2 below provides further detail). This represents a movement of £120 million from the £292 million underspend reported in June 2024 in the Provisional Outturn Statement.

Fiscal framework outturn report: 2024 - gov.scot

Table 2 – Final Outturn 2023-24 (HMT budgetary limits)
2023-24 Final Outturn
Portfolio Outturn Budget Variance Variance per Budget Category
Resource Capital Financial Transactions
£m £m £m £m £m £m
Constitution External Affairs and Culture 267 272 (5) (3) (1) (1)
Deputy First Minister and Finance 9,908 9,876 32 (15) 43 4
Education and Skills 3,795 3,851 (56) (59) 3 0
Justice 3,324 3,337 (13) (12) (1) 0
NHS Recovery, Health and Social Care 18,423 18,513 (90) (100) 9 1
Rural Affairs, Land Reform and Islands 1,061 1,133 (72) (49) (28) 5
Social Justice 6,595 6,625 (30) (7) (10) (13)
Transport, Net Zero and Just Transition 3,702 3,793 (91) (63) (27) (1)
Wellbeing Economy, Fair Work and Energy 1,222 1,326 (104) (49) (44) (11)
The Crown Office and Procurator Fiscal 196 204 (8) (8) 0 0
Total Scottish Government 48,493 48,930 (437) (365) (56) (16)
Consumer Scotland 2 2 0 0 0 0
Crown Estates 0 0 0 0 0 0
Environmental Standards Scotland 3 4 (1) (1) 0 0
Food Standards Scotland 22 22 0 0 0 0
National Records of Scotland 28 30 (2) (1) (1) 0
NHS & Teachers Pension Schemes 0 0 0 0 0 0
Office of the Scottish Charity Regulator 3 3 0 0 0 0
Registers of Scotland 6 6 0 0 0 0
Revenue Scotland 8 8 0 0 0 0
Scottish Courts and Tribunal Service 158 162 (4) (5) 1 0
Scottish Fiscal Commission 2 2 0 0 0 0
Scottish Housing Regulator 5 5 0 0 0 0
Total Scottish Administration 48,730 49,174 (444) (372) (56) (16)
Audit Scotland 16 17 (1) 0 (1) 0
Scottish Parliament 117 118 (1) (1) 0 0
Total Scottish Budget 48,863 49,309 (446) (373) (57) (16)
Funding & Post Audit Adjustments – Resource (9) (117) 108 108 0 0
Funding & Post Audit Adjustments – Capital 3 397 (394) 0 (394) 0
Funding & Post Audit Adjustments – Financial Transactions 0 (12) 12 0 0 12
Funding Adjustments – IFRS16 0 (308) 308 0 308 0
TOTAL 48,857 49,269 (412) (265) (143) (4)

15. The Provisional Outturn Statement is presented to Parliament prior to completion of audited accounts for the Scottish Government and associated bodies and is therefore subject to change.

16. The changes between Provisional and Final Outturn were a result of accounting adjustments which occurred as part of the year-end process. The main driver of the change is within the Health and Social Care portfolio and represents a significant movement in the revenue position, primarily as a result of the re-categorisation of PFI/PPP revaluation liabilities included in provisional outturn (£100 million).

17. The £412 million underspend is carried forward in full in the Scotland Reserve and utilised in 2024-25. £109 million of the capital underspend was anticipated at the Spring Budget Revision.

18. Annex A provides a reconciliation to the Scottish Government’s Consolidated Accounts versus Final Outturn statement against HM Treasury Totals.

Contact

Email: corporate.reporting@gov.scot