Planning performance statistics 2019/2020: quarterly (October to March)

Summary statistics on planning decision-making and timescales for April 2019 to March 2020 with historic data going back to 2015/2016. It is based on data we collect from local and planning authorities as part of the Planning Performance Framework (introduced in 2012).

This document is part of a collection


4. Processing Agreements

Some local authorities use processing agreements where the developer and the local authority agree on timescales for decisions. Applications subject to a processing agreement are not included in average decision time calculations.

In the final six months of 2019/20 there were 1,193 applications decided that had processing agreements, 170 fewer than in the same period in the previous year.

In quarter three 7.1% of all applications (604 of 8,528) had processing agreements, in quarter four this increased to 7.5% (589 of 7,834) of all applications having a processing agreement.

Chart 19: Proportion of applications with Processing Agreements
Stacked bar chart showing annual trends since 2015/16 in proportion of applications subject to processing agreements
Table 1: Processing Agreements, 2019/20, Quarter 3 and 4
Quarter 3 Quarter 4
Category of development Number of Decisions % Within Agreed Timescales Number of Decisions % Within Agreed Timescales
Major Applications 28 75.0% 18 55.6%
Local Applications 497 77.7% 503 80.5%
EIA Developments 2 50.0% 0 -
Other Consents 77 76.6% 68 75.0%
Total 604 77.3% 589 79.1%