Deposit return scheme for Scotland: full business case stage 1

Phase 1 of the Full Business Case (FBC) that underpins the design for the deposit return scheme for Scotland.


4 Financial Case

The key parameters and findings from the Financial Case of the Full Business Case

(FBC) Stage 1 are summarised below.

Key parameters:

  • The Financial Case is developed and reflected only from the Scheme Administrator's perspective.
  • The commercial structure adopted for the Scheme Administrator is based on the delivery model Option 2 as outlined in the Commercial Case (100% privately owned non-profit Scheme Administrator). Counting and bulking centres are procured by the Scheme Administrator. Logistics are outsourced. Reverse Vending Machines (RVMs) are procured by retailers and reimbursed by the Scheme Administrator through the handling fee.
  • The Financial Case has adopted a similar treatment of deposit inflows and outflows as the Norwegian deposit return scheme, whereby the net benefit of these flows i.e. the value of unredeemed deposits, can be recognised as revenue in the profit and loss accounts of the Scheme Administrator and applied against scheme expenses.
  • The recognition of this revenue is only enabled after sufficient evidence is collected over a period of time (for modelling purposes, from Year 0 to Year 5 inclusive) to establish an appropriate assumption around the volume of deposits that are actually unredeemed in any given period. As a result, the scheme is considered to be in steady state operation from Year 6 onwards.
  • The financial forecast and associated financial statements are developed across a ten-year period which comprises the 'Observatory Period' (Year 0 to Year 5) and steady state operations (Year 6 to Year 9).

Key findings:

  • At this stage, a number of assumptions have been made that the ultimate Scheme Administrator has the ability to determine an alternative position. A key assumption is the non-recognition of accrued cash as unredeemed deposit revenue in the profit and loss accounts until Year 6 onwards. In practice, the observatory period will be dictated by the volume and quality of evidence the Scheme Administrator is able to collate in the initial years of the scheme in order to provide sufficient comfort to auditors that a reasonable assumption with respect to the volume of deposits has been made.
  • In addition, the financial modelling has assumed that this accrued cash balance (approximately £190 million) remains within the scheme across the steady state. However, the Scheme Administrator may choose to use this in alternative ways e.g. to be applied to scheme expenses, thereby offsetting producer fees or to fund future borrowing requirements.
  • Through detailed consultation in the next stage of business planning, these alternative options will be explored to understand the implications to both the forecast revenue and costs of the scheme.

Under the current modelled assumptions, which are outlined in tabular form in the first section of this chapter:

  • The direct operational costs of the Scheme Administrator under the preferred scheme design includes a handling fee and logistics costs and, at an average of £74.7 million a year, is consistent across the Observatory Period and steady state with an initial ramp-up of costs between Year 0 and Year 1.
  • The financial modelling demonstrates that during steady state operations, the direct operational cost base will be funded by income from unredeemed deposits (42%) and sale of materials (26%) with the balance from the producer fee (32%). Until this point, the producer fee reflects 71% of the revenue base with sale of materials attributing 29%.
  • The indicative producer fee during the observatory period equates to £48.4 million or 3.3p per container which is expected to reduce to £25.9 million or 1.5p per container during steady state operations. At this stage, the producer fee is calculated on an overall scheme basis. However, a producer fee by material type will be derived by the Scheme Administrator. Indicative figures will be developed in consultation with the private sector during the next stage of business planning.
  • The overall investment required by the Scheme Administrator is an upfront capital injection of £27.6 million. The investment will be used to acquire and fit out facilities with counting and bulking equipment. The funding of the facilities is expected to be 100% debt-financed and therefore requires no upfront capital contribution from the public sector. The cost of this debt service is passed through to producers through the producer fee as part of Extended Producer Responsibility (EPR).
  • Sensitivity analysis demonstrates that the producer fee is sensitive to changes in the handling fee, sale of materials revenue and the logistics fee.

4.1 Introduction

4.0 The purpose of this section is to set out the forecast financial implications of delivering the preferred scheme design (as set out in the Socio-Economic Case) under the proposed structure (as described in the Commercial Case). As a result, the Financial Case is developed to reflect only the perspective of the Scheme Administrator, who will be responsible for the financial management and execution of the scheme.

4.1 The Financial Case outlines the key financial assumptions underpinning the operations of the Scheme Administrator and demonstrates the indicative financial position through the development of financial statements (profit and loss, balance sheet and cash flow statements) over a ten-year period. Overall, the Financial Case presents a view of the key revenue streams, capital investment and on-going costs required for delivery of the scheme in order to conclude on the affordability of the preferred scheme design.

4.2 Background

4.2 The Full Business Case (FBC) is based on the preferred scheme design as outlined in the Commercial Case.

4.3 Approval of the FBC Stage 1 (this document) and FBC Stage 2 (next stage) and the proposed final scheme design, will enable the progression of the necessary legislative and regulatory requirements. Therein, implementation of the preferred scheme design will be driven by the controls and framework outlined in the Management Case.

4.4 This FBC also identifies the on-going necessary capital and revenue expenditure associated with the Scheme Administrator. There figures are, however, still pre-market i.e. the figures are not informed by a competitive tendering exercise. It is intended that these will help to inform the development of a business plan for the Scheme Administrator, as part of FBC Stage 2.

4.3 Financial Modelling Assumptions

4.5 The FBC is based on the latest assumptions available. In the development of this document there has been consultation with various DRS schemes in other jurisdictions to leverage their experience and insights to both determine and benchmark the current cost and income assumptions underlying the Financial Case. Detailed consultation will be conducted on the final preferred scheme design with local authorities and private sector stakeholders in order to validate the modelled assumptions as part of detailed business and implementation planning.

4.6 The financial plans will be updated once the detailed business planning exercise commences (FBC Stage 2).

4.7 Table 27 sets out the key assumptions and methodology used in the financial modelling:

Table 27: Financial Modelling Key Assumptions

Area

Sub-Heading

Description

Cost base

2018/19 forecast outturn

Cost assumptions have been developed in 2018/19 which are escalated to the commencement of the scheme.

Period modelled

Ten years (2019/20 to 2028/29 inclusive)

The financial model has been developed over a ten-year annual basis whereby Year 0 (2019/2020) reflects the year directly before the scheme is launched and Years 1-9 reflect the forecast financial position of the Scheme Administrator following launch on 1 April 2020. It should be noted that the date of scheme launch is a modelling assumption used to undertake the investment appraisal and may in practice vary in accordance with ministerial approval and business and implementation planning.

The rationale for modelling one year prior to scheme launch is to reflect the revenues and expenses expected to be incurred by the Scheme Administrator in establishing the scheme to correctly reflect affordability.

The revenue and cost base modelled across Year 0 to Year 1 reflects a start-up period where variability is expected in revenues and costs as the Scheme Administrator becomes established and operations achieve a steady state (modelled from Year 6 to Year 9). In the start-up phase, scheme revenues are heavily driven by the producer fee and sale of materials revenue whilst costs ramp-up as capital investment activity occurs and operational functions are established and reach an efficient run rate.

As outlined in Cash Inflows/Outflows below, Year 6 to Year 9 is considered the true reflection of steady state operations as up to this point, the Scheme Administrator will not recognise all available cash as revenue on the profit and loss account. Over the course of Year 0 to Year 5, referred to as the Observatory Period, the Scheme Administrator will be collecting evidence on consumer behaviour to support the establishment of an assumption that reflects the amount of deposits that are never to be redeemed in a given period, and therefore can be recognised as revenue.

Deposit level

20p

Under the preferred scheme design, the deposit level is set at 20p. It is assumed to be constant across the entire modelled period and therefore drops in value in real terms as a result of inflation.

Target recycling rate (TRR)

90%

Under the preferred scheme design, the annual target recycling rate is set at 90%. That is, it is assumed that of all eligible DRS material in the scheme, 90% will be returned and a 20p deposit redeemed.

The model applies a ramp-up assumption to demonstrate performance against the target in the initial years of the scheme.

Cash inflows and outflows

Deposits in/ Deposits out

As outlined in the Commercial Case, the treatment of the deposits has been modelled based on the Norwegian DRS scheme. A key factor of this scheme is that the Scheme Administrator is treated as operating in a principal capacity in respect of deposit inflows and outflows, as compared to an agency capacity. The difference is that as a principal the Scheme Administrator will recognise the deposits as revenue and expenditure in its profit and loss account, whereas an agent would be responsible for managing the collection and disbursement of the deposits, but they would not be recognised as revenue and expenditure in the profit and loss account.

The rationale for the principal capacity is that there is a clear distinction of receipts in (Scheme Administrator and producers) and payments out (Scheme Administrator and retailers).

  • Deposits In (Revenue) - Producers are required to provide a report to the Scheme Administrator at an agreed periodicity, typically monthly, outlining the number of containers that have been sold to wholesalers in this period. The Scheme Administrator will invoice the producers for the relevant amount based on the report.
  • Deposits Out (Expenditure) - Retailers will in the first instance provide consumers with their deposit refund for redeemed DRS material. Following this event, they will invoice the Scheme Administrator at an agreed periodicity, for reimbursement of deposits paid.

In any given period, it is possible that the value of deposits paid into the Scheme Administrator may exceed the value of deposits that are redeemed. Based on the Norwegian DRS scheme (and DRS schemes in other jurisdictions), the Scheme Administrator is in principle able to recognise and, therefore, obtain the net benefit between the revenue and expenditure in relation to the deposits (referred to in this Financial Case as unredeemed deposits). The unredeemed deposits can then be used to partially fund the scheme expenses.

See next section for the assumptions underpinning how and when unredeemed deposits can be recognised by the Scheme Administrator.

Income

Unredeemed deposits

As outlined above, unredeemed deposits arise where a deposit has been paid to the Scheme Administrator by the producer on an eligible container, but the container has not been (and will not be) returned to a retailer by a consumer and, therefore, the deposit value is not paid out of the scheme.

Under this circumstance, the Scheme Administrator is (subject to the appropriate sign-off from their external auditor) able to recognise the net benefit as 20p per unredeemed container per period.

In practice, the Scheme Administrator will need to make a determination on the following two elements in order to ascertain the total net benefit from unredeemed deposits:

1. The volume of deposits that will be classified as unredeemed deposits and therefore can be used to offset scheme expenses

2. The timing from which the Scheme Administrator can provide sufficient evidence to allow audit sign-off for the recognition of the unredeemed deposits in the profit and loss account.

In respect of Item 1, the Scheme Administrator will need to collect evidence of the volume of deposits that are not redeemed over a sufficient period of time in order to develop a commercial assumption on the appropriate amount to be deemed 'unredeemable'.

For modelling purposes, the value of unredeemed deposit revenue is calculated as 20p multiplied by the volume of unredeemed containers per period derived in correlation to the target recycling rate i.e. where the TRR is 90%, the number of unredeemed containers is expected to be 10% of all containers in the DRS.

In respect of Item 2, the sufficient period of time over which this assessment should be made will be a matter for justification by the Scheme Administrator based on the quality and volume of evidence that is collected. For modelling purposes, it is assumed that a five-year Observatory Period will be required to enable the development of the evidence base to satisfy auditors. Unredeemed deposits will therefore be recognised from Year 6 to Year 9 (the steady state period) in the profit and loss account.

Sale of material

The Scheme Administrator has the ability to sell eligible DRS material that has been returned through the scheme. The modelling assumes that 97% of eligible DRS material that is returned is sold.

100% of returned material is not assumed to be saleable based on consultation with existing schemes in other jurisdictions who have indicated that approximately 2-3% of material may be damaged or not of saleable quality as it passes through the supply chain i.e. glass bottles may be broken during sorting.

The model applies a £/tonne rate to the volume of returned material to calculate the total revenue. The rate assumptions are applied at a material level i.e. PET, aluminium/steel, glass (flint), glass (brown) and glass (green) to accurately reflect the relativity of market rates. Whilst it is acknowledged that aluminium and steel prices vary in the market, the two materials have been aggregated in the financial modelling and a revenue rate closer to market rates for aluminium has been adopted as steel material comprises only 1% of the forecast volume.

The £/tonne rate per material is outlined below:

Material type Revenue rate (£/tonne)
PET £200
Aluminium and steel cans £1,300
Glass (flint) £17
Glass (green) £6
Glass (brown) £12

The rates adopted for modelling purposes are based on a survey of spot rates available for each material type.

The model also has the ability to apply a sensitivity to the relevant rates to reflect the volatility of material prices in both domestic and international markets.

Producer fee

As a result of the Extended Producer Responsibility (EPR) nature of the scheme, the onus is on producers of the eligible DRS material to support the efficient establishment (including set-up costs) and financial management of the scheme. The producer fee, which is recognised by the Scheme Administrator as revenue, is set on a cost-recovery basis. The fee will vary but is calculated each period (in practice, monthly) and should offset all scheme expenses not recovered by other revenue streams. This includes direct operating costs and debt service required to fund upfront capital.

Based on the current forecast, the following contributions are required from producers across the start-up and steady state operations of the scheme:

1. Start-up period (Year 0 to Year 5) - Producer fee 3.3p per container, or on average £51 million a year, as a result of being unable to recognise the benefit of 'never to be redeemed' deposits until Year 6

2. Steady-state period (Year 6 to Year 9) - Producer fee 1.5p per container, or on average £30 million a year

Other

The Scheme Administrator will also be able to generate revenue through interest earned on cash balances which is assumed at a rate of 1% per annum.

Costs

Workforce

Workforce costs comprise a lean workforce required to execute the functions of the Scheme Administrator and a workforce to operate the counting and bulking centre facilities.

Following establishment of the scheme, the workforce costs for both system administration and counting and bulking centre operation equate to an average of £3.2 million a year.

The workforce cost has been determined based on a high-level assessment of staffing requirements based on consultation with existing schemes in other jurisdictions.

Property

The economic modelling has indicated that the supply of throughput in the scheme could be managed by the establishment of counting centres which comprise both a bulking point and counting apparatus at each facility. This assumption has been adopted for financial modelling. However, in practice the requirement and timing will be determined by the Scheme Administrator based on property availability and suitability to support the functions of the DRS.

Properties are assumed to be acquired in Year 0 where construction of each facility is then completed before commencement of the scheme in Year 1.

Properties and related equipment are depreciated on a straight-line basis for the term of their respective useful life as outlined below:

Buildings - 25 years

Counting apparatus - seven years

Technology - three years

See Capital and Revenue Requirements for further details.

Logistics

As currently modelled, logistics costs in the steady state period reflect approximately 21% of direct operating expenses.

A logistics contract is expected to be entered into for the provision of pickup and delivery services from material return points across the network i.e. pickup from retailers and delivery to the relevant counting centre facility.

The costs are forecast by applying an estimated £/tonne rate multiplied by the relevant volume of returned material. Two rates are used to distinguish material that is collected from an automatic return point i.e. (i) material that is compacted through an RVM or (ii) a manual return point where material is collected and stored manually prior to pick-up. It is assumed that 85% of all material is collected through an automatic return point whilst 15% is manually handled.

As a result, the financial modelling forecasts an average logistics fee of £16.5 million a year in steady state, comprising the following breakdown:

Automatic handling - £12.9 million a year.

Manual handling - £3.6 million a year.

The rates underpinning the forecast are pre-commercial negotiations and do not assume any route optimisation factors and as a result may vary upon detailed consultation and negotiation with suppliers.

Cost of fraud

Evidence from established jurisdictions indicates that a level of fraud should be anticipated within the scheme.

The fraud can occur in a number of ways. Some examples include:

1. Ineligible materials are accepted manually by retailers and deposits are paid. However, material is ineligible for sale and/or potentially contaminates eligible sale material.

2. Ineligible materials are accepted through the automatic RVM and deposits are paid. However, material is ineligible for sale and/or potentially contaminates eligible sale material.

3. Illegally manipulating/tampering with RVMs to claim additional deposits for the same material.

Ineligible materials can be containers trafficked from outside the jurisdiction of the scheme, or alternatively, locally-produced containers that are made of material that is not included within the remit of scheme i.e. HDPE.

The financial implications of the various types of fraud can include a decrease in unredeemed deposits revenue, a decrease in sale of materials revenue and potentially an increase in handling fees due to the introduction of additional material into the DRS eco-system.

The model assumes that, in most instances, the risk of this expense sits with the Scheme Administrator and as a result adopts an expense factor associated with fraudulent behaviour as 20p multiplied by 1.5% of the number of containers. 1.5% has been adopted based on the experience of existing schemes in other jurisdictions.

While it is anticipated that fraudulent activity will be monitored and managed by the Scheme Administrator and the related regulatory framework, the model holds this assumption constant across the modelled period.

Communications

It is recognised that a critical success factor to achieving the scheme's objectives is effective communication across various groups of stakeholders including producers, retailers and consumers.

As a result, the Financial Case provides an upfront allowance for communications expenditure equating to £1 million in Year 0 which modulates to approximately £400k a year upon scheme commencement.

Handling fee

As currently modelled, the handling fee in the steady state period is on average £50.6 million a year and reflects the largest scheme expense at approximately 65% of the direct operating cost base.

The handling fee intends to compensate retailers for their role in accepting and storing returned material until it is collected by the scheme logistics partner. The handling fee will vary depending on whether the retailer manually processes and stores material or automatically does this through the use of an RVM.

Under the preferred scheme design, four types of return points are modelled[53]:

Return Point 1 - Return to Hospitality Restaurants and Cafes (HoReCa) - Closed loop (manual handling)

Return Point 2 - Return to HoReCa - Open loop (manual handling)

Return Point 3 - Return to Retail (automatic handling)

Return Point 4 - Return to Retail (manual handling)

The handling fee is calculated by forecasting the costs expected to be incurred by retailers in accepting and storing returned material, and considers this cost against the forecast of material expected to flow through the particular return point, to calculate a £/container rate that is then multiplied by the total material.

The cost base that forms the numerator in the above methodology will vary for manual vs automatic handling processes. For example, the handling fee for Return Point 3 will be calculated by estimating the establishment and run costs of installing an RVM(s), in addition to compensating the retailer for the value of lost retail space and lost staff time.

The average handling fee a year is estimated as follows:

Automatic handling return point (Return Point 3): 3.1p/container

Manual handling return points (weighted average across Return Points 1, 2 and 4): 1.5p/container

Corporate Structure

Not for profit (NFP)

The model is developed in accordance with the Commercial Case that identified a not-for-profit corporate structure as the preferred delivery route.

Ownership

Private sector

The Scheme Administrator is expected to comprise various private sector participants that are likely to establish a Special Purpose Vehicle (SPV)/Independent entity to execute the objectives of the scheme.

The key financial implications are:

1. Debt is expected to be financed at commercial rates

2. There are no affordability/public sector budget implications

Tax

Corporation Tax

The vehicle is expected to be exempt from Corporation Tax as a result of the not-for-profit status.

VAT

The goods and services administered by the scheme are expected to be exempt from VAT as a result of the not-for-profit status.

Other

PAYE tax and National Insurance contributions are estimated at 20% of the salary cost base and have been built into and reflected in the workforce cost estimates.

Assets

Counting centre buildings and equipment

An upfront capital investment of approximately £27.6 million is required in order to fund the acquisition and establishment of counting centre facilities.

The capital investment comprises three asset classes which are considered within the forecast:

Asset Class 1 - Counting centre buildings (useful life: 25 years)

Asset Class 2 - Counting centre apparatus (useful life: 7 years)

Asset Class 3 - Scheme administrator equipment (software) (useful life: 3 years)

Replacement capital expenditure of approximately £7.5 million is expected in Year 8 of the operating scheme in order to replace the counting centre apparatus at each facility which has a useful life of seven years (Asset Class 2). This is expected to be funded through available cash balances.

A replacement of scheme administration software is not anticipated as a capital investment in the modelled period.

The upfront capital investment is expected to be 100% debt-financed at a commercial rate of 2% (see Capital and Financing for further details) whilst replacement capital expenditure is expected to be funded through available cash balances.

All assets created are assumed to be recognised on the balance sheet of the Scheme Administrator and be depreciated over their useful life in accordance with the straight-line depreciation method.

It is assumed that retailers operating automatic return points will self-fund the acquisition/lease of RVMs used in compliance with their obligations under the scheme. As such, no capital investment is required by the Scheme Administrator for this equipment.

Working Capital

Debtor days

Creditor days

30 days

4.4 Capital and Revenue Requirements

4.4.1 Introduction

4.8 As set out in the Commercial Case and above, the expectation is that the DRS will be delivered by way of a private sector not-for-profit vehicle. On this assumption, there will be no direct capital or revenue budgetary impacts to the public sector budget.

4.9 As such, the forecast capital costs and revenue costs outlined below are expected to be incurred by the Scheme Administrator in delivering the DRS.

4.4.2 Capital Investment

4.10 The capital costs associated with delivery of the final scheme design have been estimated based on information from various sources including consultation with existing schemes in other jurisdictions, preliminary studies commissioned by Zero Waste Scotland and the Scottish Government and publicly available information.

4.11 The upfront capital requirement for the Scheme Administrator is estimated to be £27.6 million in Year 0.

4.12 Table 33 sets out the elements of capital expenditure required, the estimated costs, and the basis of these costs.

4.13 As outlined under section 4.3, it is assumed that retailers operating automatic return points will self-fund the acquisition/lease of RVMs. As such, no upfront capital investment is required by the Scheme Administrator for this equipment. The economic modelling estimates that 3,100 RVMs will be operational within the network of participating retailers. The Scheme Administrator will offset the costs incurred by retailers through the handling fee (see Table 28 for further detail).

Table 28: Scheme Administrator Initial Capital Investment Requirements

Element

Cost (£ million)

Description

Counting and bulking centre building

£20.9 million

For the purposes of modelling, it has been assumed that industrial facilities will be required with a combined function of bulking and counting of material.

Reflecting a conservative case, it has been assumed that the Scheme Administrator will purchase all facilities upfront and manage them, directly.

In practice, the Scheme Administrator may be able to reduce the upfront capital investment by staggering the acquisition of these facilities as scheme operations ramp up and surplus cash funds are available or, alternatively, lease these facilities or pay a network operator fee depending on availability and suitability of infrastructure across the Scottish network. The associated costs of alternative options will be considered in further detail during the business planning phase.

Counting centre equipment

£6.4 million

Each facility will be fitted out with counting and sorting machines. As a result, the estimated cost per facility is £1.6 million.

This equipment is expected to be replaced following the end of its useful life of seven years at an increased cost of £7.5 million reflecting inflation of 2%.

Similar to above, there may be alternative options for mitigating part or all of the upfront capital investment requirements through leasing equipment or paying a network operator fee. The associated costs of alternative options will be considered in further detail during the business planning phase.

IT infrastructure

£0.3 million

It is expected that £0.3 million of upfront capital expenditure will be required to establish the Scheme Administrator's IT infrastructure.

Total

£27.6 million

4.4.3 Capital Financing

4.14 The funding for the capital elements will be developed as part of the business planning process, but for the purpose of this Financial Case a conservative position has been adopted and it has been assumed that upfront capital elements will be funded 100% through commercial borrowing. The business planning process will consider whether through-life capital requirements will be funded by excess surplus, commercial borrowings or leases.

4.15 Table 29 below demonstrates the estimated finance required and the financing assumptions adopted in the Financial Case.

Table 29: Scheme Administrator Initial Capital Investment Financing

Element

Cost (£ million)

Delivery Route / Funding

Counting and bulking centre building

£20.9 million

It is assumed that the private sector participants in the industry-based group will comprise beverage and retail industry members.

As a result, a proxy of the assumed cost of capital that could be accessed by these participants in the commercial borrowing sector has been adopted.

This all-in cost of capital rate is 2% a year and is assumed to be secured against the assets of the scheme.

As identified above there may be alternative options for either reducing the upfront capital investment requirement (staggering of investment) or financing through alternative means (leasing, producer loan, and cash surpluses) and these will be considered further in the FBC Stage 2.

IT Infrastructure

£0.3 million

Counting Centre Equipment

£6.4 million

Total

£27.6 million

4.16 Should the business planning process identify alternative funding mechanisms, with more competitive interest rates, then this would clearly have a positive impact by reducing overall costs of the scheme.

4.4.4 Optimism Bias

4.17 As the project has evolved, the value of the optimism bias has been utilised to review any proposed scheme designs in line with HMT Treasury guidance. The variation created by optimism bias has been held constant across the Socio-Economic Case and Financial Case during the development of this document as market testing has not formally been conducted in respect of key revenue and cost drivers.

4.18 Notwithstanding the above, a contingency allowance has been reflected in the financial modelling by the use of conservative estimates i.e. no assumption of cost optimisation over time and methodologies adopted such as assuming all upfront financing is 100% debt funded. As a result, this allows decision making to move forward with confidence in respect of the quality and appropriateness of the design and the cost planning.

4.4.5 Revenue Requirements

4.19 The costs associated with the Scheme Administrator can be summarised into two key elements - the direct operational costs (including the handling fee that is paid to the retailers for undertaking the collection of the materials) and non-operational costs.

4.20 As part of ensuring the ongoing success of the scheme, it is envisaged that a regulatory framework will be established to mandate the key obligations of the Scheme Administrator. In addition, a regulatory body will need to be established in order to manage this regulatory function. On this assumption, there will a direct capital or revenue budgetary impact to the public sector. However, a regulatory compliance fee has been assumed within the direct operational cost base of the Scheme Administrator to offset this expense.

Costs of Scheme Administrator

4.21 The categories comprising the direct operational costs of the Scheme Administrator have been derived with reference to existing schemes in other jurisdictions and the preferred scheme design for Scotland.

4.22 A summary of the breakdown and proportionality of the direct operational costs is outlined in the diagram below (Figure 10), following which Table 30 outlines the detailed description underlying each specific element of the direct operating cost base and, in addition, the non-operational costs including depreciation and interest payable.

Figure 10: Breakdown of Scheme Administrator's Direct Operational Costs under Steady State

Figure 10: Breakdown of Scheme Administrator's Direct Operational Costs under Steady State

Table 30: Description of Scheme Administrator's Cost Elements

Note: averages outlined in the table reflect the average steady state cost of operations

Element

Average cost a year (£ million)

Description

Direct Operational Costs

£78.2 million

Staffing

System administration costs (Scheme Administrator)

£0.8 million

On average, workforce costs for the administration of the scheme are estimated at £790,000 a year. These costs comprise the personnel required to undertake the management and administrative functions of the scheme. However, it does not include the operational workforce required in the counting centres (see below).

Whilst the mix of employees will be assigned during the business planning phase, the cost base assumes a 20% allowance for tax and National Insurance contributions across the workforce.

50% of this cost base is assumed to arise in Year 0 where recruitment of key personnel will be required to support the establishment of the scheme prior to launch in Year 1.

Workforce costs - counting centre

£2.5 million

The workforce employed across four counting centres is estimated to cost on average £2.5 million a year. Based on a high-level assessment of workforce requirements as informed by consultation with existing schemes in other jurisdictions, the workforce is expected to comprise supervisory and management staff, counting and sorting machinery specific staff, administrative and general facility staff and other technical staff.

Whilst the mix of employees responsible for scheme administration and counting centre management and operation will be assigned during the business planning phase, each cost base assumes a 20% allowance for tax and National Insurance contributions across the workforce.

50% of this cost base is also assumed to arise in Year 0 where recruitment of key personnel will be required to support the establishment of the facilities prior to launch in Year 1 which will ramp up to full capacity in Year 1.

Ongoing operational costs

System administration costs (Scheme Administrator)

£0.5 million

On average, ongoing operational costs of the Scheme Administrator are estimated at £500,000 a year.

A detailed breakdown of the items assumed in this cost base can be found in the Socio-Economic Case. However, broadly the costs comprise general running expenses of the office facilities including rental, utilities and supplies.

General operating costs - counting centre

£1.2 million

Ongoing operational costs for the total number of counting centre facilities is estimated at an average of £1.2 million a year. Assuming an equivalent capacity and fit-out of each counting centre, this results in an average spend of approximately £300,000 a year per counting centre.

This cost base comprises rental, utilities, supplies, cleaning and other ongoing costs.

Logistics costs (both automatic and manual collection)

£16.5 million

The logistics cost is derived by multiplying the volume of material in tonnes expected to flow through each of the return point configurations by a respective £/tonne rate. There are two rate variations based on whether material has been collected through an automatic return point or manual return point. The breakdown of the average annual logistics fee under steady state is as follows:

a) Logistics fee for collection of manually handled material (£3.6 million a year)

b) Logistics fee for collection of automatically compacted material (£12.9 million a year)

Based on discussions with existing schemes in other jurisdictions, it is assumed that 85% of material that is collected flows through an automatic return point whilst only 15% is collected from return points where material is manually handled and stored.

Communications

£0.5 million

Communications and marketing are expected to be a recurrent expense for the Scheme Administrator in order to support successful scheme implementation.

In Year 0, the communications expenses is estimated at £1 million to support development and delivery of educational material for initial circulation. However, the average cost of communications from Year 1 onwards is estimated to be £460,000 a year, reflecting a typical annual marketing cycle.

Cost of fraud

£5.3 million

The inclusion of an expense reflecting the cost of fraud is a conservative tool to understand the sensitivity of the scheme to the loss of revenue due to fraudulent behaviour.

The cost methodology has been derived through consultation with other existing schemes which have advised that 1.5% of total deposits received is an indicative cost of fraud allowance. While it is difficult to predict if and how the Scottish scheme will experience similar levels of fraudulent behaviour as other jurisdictions, the scheme appears to be recurrently affordable despite the inclusion of this expense.

In practice, it is expected that this allowance will vary and reduce from period to period as the Scheme Administrator will be responsible for actively monitoring and addressing fraudulent behaviour.

Regulatory compliance fee

£0.3 million

An average cost of £250,000 a year is estimated to reflect the regulatory compliance fee paid by the Scheme Administrator to the new regulatory body.

An original estimate was provided during the development of the OBC which has been escalated based on the development of the scheme design and the application of inflation at 2%.

Non-Operational Costs

£2.2m

Depreciation

£1.8 million

Depreciation is modelled on a straight-line basis on an initial capital investment of £27.6 million.

The breakdown of the average depreciation forecast across the three asset classes outlined in section 4.3 is as follows:

Asset Class 1 (buildings) - £0.8 million (useful life: 25 years)

Asset Class 2 (equipment) - £0.9 million (useful life: 7 years)

Asset Class 3 (software) - £0.1 million (useful life: 3 years)

Interest Payable

£0.4 million

The average interest expense of £422,000 a year is calculated on the balance of the initial capital investment of £27.6 million which is assumed to be 100% commercially debt-financed at a rate of 2%, repayable over a ten-year term.

Cost of capital assumptions are outlined in section 3.4.3.

4.4.6 Handling Fees

4.23 The principle underlying the handling fee is to compensate retailers for their role in accepting and storing returned DRS material until it is collected by the logistics partner.

4.24 The modelling estimates the average annual handling fee to retailers across the network as £50.6 million a year.

4.25 In practice, the amount of the handling fee that is paid to each individual retailer will vary based on the volume of material that flows through their return point. However, the calculation methodology used to determine the £/container rate upon which the fee is calculated is consistent.

4.26 There are two elements that comprise the breakdown of the overall handling fee. The first element intends to reflect the estimated costs faced by retailers who process material automatically through the use of an RVM. The second element reflects the estimated costs faced by retailers who manually accept and store returned material.

4.27 As outlined in section 4.3, the preferred scheme design segments the two elements of the handling fee by building up the expected cost base of these retailers across various return point configurations. The expected type and collection configuration contemplated within the scheme modelling is:

a) Return Point 1 - Return to HoReCa - Closed loop (manual handling)

b) Return Point 2 - Return to HoReCa - Open loop (manual handling)

c) Return Point 3 - Return to Retail (automatic handling)

d) Return Point 4 - Return to Retail (manual handling)

4.28 For retailers that are classified under the Return Point 3 configuration, the handling fee has been calculated as 3.1p per container. To derive the handling fee paid to this segment, this container rate is then multiplied by 85% of the total volume of DRS material which is the volume expected to pass through this return point. This results in the value of the first component of the overall handling fee, an average fee of £47 million a year.

4.29 The residual £4 million a year comprises the handling fee to retailers across Return Points 1, 2 and 4 which are expected to manually handle 15% of the DRS material. Each return point has an individual £/container rate that is applied in the modelling. However, the weighted average handling fee across the three return points is 1.5p per container.

4.30 The cost base that is assumed for each return point operator comprises a number of cost categories. While the underlying values attributed to each cost category are yet to be tested formally in the market, they have been informed through preliminary consultation with relevant stakeholders and benchmarking against existing schemes in other jurisdictions. The cost categories included in the calculation per return point are outlined in Table 31 below.

Table 31: Handling Fee Cost Categories applicable per Return Point

Cost Category

Return Point 1
HoReCa -Closed loop (manual handling)

Return Point 2
HoReCa - Open loop (manual handling)

Return Point 3
Large retailers (auto handling)

Return Point 4
Small to medium retailers (manual handling)

Establishment costs

Installation cost

N/A

Note 1

N/A

Note 1

Note 2

N/A

Note 1

Running costs

RVM lease cost

N/A

Note 1

N/A

Note 1

Note 2

N/A

Note 1

Materials cost

Note 3

Note 3

N/A

Note 4

Note 3

Ongoing costs

Note 3

Note 3

N/A

Note 4

Note 3

Compensatory costs

Lost retail space

N/A

Note 5

Note 7

Note 6

Note 7

Lost staff time

N/A

Note 5

Note 7

Note 6

Note 7

Note 1

As per the preferred scheme design, Return Points 1, 2 and 4 are assumed to manually handle and store returned DRS material. As a result, there are no RVMs expected to be leased and installed across these return points and no associated establishment cost. Economic modelling estimates that there will be approximately 14,300 participating manual return point locations across the Scottish DRS network.

Note 2

Under the base case, retailers are assumed to lease all RVM equipment. This assumption is on the basis that retailer participation in the DRS is not core business and therefore assets utilised in the execution of these obligations are not likely to be acquired.

There are also ongoing circular economy benefits to leasing the equipment, including reduction of asset stranding and obsolescence risks.

While it is acknowledged that a number of retailers may choose to acquire the equipment where financially feasible, the drivers influencing this purchasing decision have not been tested formally with the market and as such, an assumption that all 3,100 units required across the network will be leased has been adopted.

As a result, the estimated leasing fee is derived by considering the expenses associated with operating an RVM including an allowance for depreciation and cost of capital, maintenance of the RVM, operating costs and insurance.

Note 3

It is assumed that retailers operating manual return points will be required to acquire materials to sort, label and store material appropriately prior to pick-up by the logistics partner.

Materials and ongoing costs are expected to comprise recycle-appropriate bags for storing returned material, labels and tags to indicate stored material, containers for collection prior to sorting and bagging, and writing materials among other miscellaneous items.

Note 4

Cost of materials and ongoing costs associated with an RVM are included within the leasing fee assumed per unit.

Note 5

Retailers classified under Return Point 1 are bars and restaurants that will not be required to accept DRS-eligible material that has not been sold on premise. As a result, these retailers will not be compensated for lost retail space and lost staff time, as they will only be required to accept material that would typically be handled/recycled in the usual course of their business notwithstanding the DRS.

Note 6

The value of retail space is estimated with respect to the number of RVM machines that are fitted out within each individual return point. For retailers operating automatic return points, this item is expected to reflect the largest cost driver within the handling fee cost base. As a result, the overall fee is sensitive to changes in this estimate.

Similarly, the estimate to be determined in valuing lost employee time relates to time spent interacting with the RVM i.e. emptying compacted material in preparation for collection. The assumptions adopted for both these estimates will need to be tested formally with relevant stakeholders as part of the business planning phase.

Note 7

The rationale behind compensating retailers for lost retail space and employee time is consistent across automatic and manual return point configurations. However, the value of compensation related to retail space is relatively reduced for manual return points as compared to automatic return points. This is because the amount of retail space expected to be displaced as part of accepting DRS material is related to manually storing these items prior to collection as compared to the space being displaced due to accommodating a single or multiple RVMs.

4.4.7 Revenue Funding

4.31 As outlined in the financial modelling assumptions section, there are three key sources of revenue associated with operation of the scheme; unredeemed deposit revenue, sale of materials revenue and the producer fee.

4.32 The first two sources of revenue are derived from the operations of the scheme and are typically impacted by performance against the target recycling rate and the volume and quality of recycled material within the scheme, respectively. The latter is a contribution required from producers in order to recover against the scheme expenses that are not offset by other revenue sources.

Operational revenues

4.33 The underlying assumptions comprising the estimated revenue forecast have been derived with reference to existing schemes in other jurisdictions and the preferred scheme design for Scotland.

4.34 A summary of the breakdown and proportionality of the scheme revenues across both the observatory period (Year 0 to Year 5) and under steady state operations (Year 6 to Year 9) is outlined in Figure 11 and Figure 12 below. The key variance between diagrams is the existence of unredeemed deposits in the latter, whereby it is expected that the Scheme Administrator has collated and demonstrated a sufficient base of evidence to support recognition of unredeemed deposit revenue for application in the scheme. Following these diagrams, Table 32 outlines the detailed description underlying each specific element of the operating revenue base and non-operating revenues including interest earned on the scheme's cash balance under steady state operations.

Figure 11: Breakdown of Scheme Administrator's Operating Revenue Sources Observatory Period

Figure 11: Breakdown of Scheme Administrator's Operating Revenue Sources Observatory Period

Figure 12: Breakdown of Scheme Administrator's Operating Revenue Sources Steady State

Figure 12: Breakdown of Scheme Administrator's Operating Revenue Sources Steady State

Table 32: Description of Scheme Administrator's Revenue Elements

Note: averages outlined in the table reflect the average steady state revenue

Element

Average Revenue a year (£ million)

Description

Operational Revenue

£80.8 million

Unredeemed deposits

£33.9 million

At 42% of the revenue base under steady state operations, unredeemed deposit revenue reflects the Scheme Administrator's largest source of revenue, once recognised.

Under the preferred scheme design, unredeemed deposits revenue is calculated as 10% of the total volume of DRS material multiplied by the deposit rate of 20p per unredeemed container per period.

In accordance with the treatment of deposit inflows and outflows, under the Norwegian scheme, the DRS Scheme Administrator is only able to recognise the net benefit of these scheme inflows/outflows as revenue on the profit and loss account once a sufficient base of evidence has been established to demonstrate the volume of containers deemed to be 'unredeemed' is reasonable, and this is approved by the Scheme Administrator's external auditor.

For the purposes of modelling, it is assumed that a five-year observatory period will be sufficient to collate the base of evidence required and, therefore, the net benefit of deposits paid by producers and deposits paid to retailers is able to be recognised from Year 6 onwards.

See Impact on Profit & Loss Account below for further detail.

Sale of materials revenue

£20.9 million

Sale of materials revenue is derived once returned DRS material received by the Scheme Administrator is sold onwards to relevant material markets.

This revenue source is sensitive to the volatility of material markets and external prices. However, the model assumes the following rates which are based on a survey of market rates available in each material market:

Material type Revenue rate (£/tonne)
PET £200
Aluminium and steel cans £1,300
Glass (flint) £17
Glass (green) £6
Glass (brown) £12

The breakdown of total sale of materials revenue by material type is outlined below. The table demonstrates that aluminium (99% of volume) and steel (1% of volume) containers contribute significantly to this revenue representing more than 70% of the revenue base.

Material type Average Steady State revenue (£ million a year
PET £4.7
Aluminium and steel cans £14.7
Glass (Flint) £1.0
Glass (Green) £0.3
Glass (Brown) £0.2

The average volume of materials by type is outlined in the table below:

Material type Average volume of materials (tonnes a year)
PET 21,191
Aluminium and steel cans 11,121*
Glass (flint) 56,813
Glass (green) 48,036
Glass (brown) 13,223

*99% Aluminium

Producer fee

£25.9 million

As outlined in section 3.3, Extended Producer Responsibility places the onus on producers of eligible DRS material to support the efficient establishment and financial management of the scheme.

As a result, the producer fee, which is recognised by the Scheme Administrator as revenue, is set on a cost-recovery basis and is intended to offset all operational expenses associated with the scheme including debt service.

During the observatory period (Year 0 to Year 5) where the Scheme Administrator is not recognising the net benefit of unredeemed deposit revenue, the producer fee at £48.4 million a year is significantly higher than the contribution required under steady state operations (Year 6 to Year 9).

Given the cost base outlined in section 3.4, the producer fee is calculated as an average of £25.9 million a year under steady state operations.

While the producer fee is likely to vary period to period in practice, the methodology adopted in the model is consistent with existing schemes in other jurisdictions and upholds the cost-recovery principle.

On a container basis, the average annual contribution required by producers is calculated as 3.3p per container during the observatory period and reduces to 1.5p per container once steady state operations are achieved.

During the business planning phase, further information will be gathered in respect of the processing costs per material in order to derive a producer fee by material type.

4.5 Impact on Profit and Loss Account

4.35 The preferred option assumes a not-for-profit model whereby the entity can make surpluses, but these will not be distributable.

4.36 There are several important interdependencies between the producer fee, unredeemed deposits and handling fee. Summary profit and loss projections for a ten-year period from the initial set-up of the scheme through to the steady state operations are set out in Table 33.

4.37 A summary of the direct scheme expenses comprising gross margin are represented in the Figure 13 and Figure 14 below. These illustrate the financial implication of the Extended Producer Responsibility principle, which requires the producers to contribute to the scheme the costs of administration that are not offset by existing sources of revenue. On average, the scheme requires producers to contribute an average of £48.4 million a year or 3.3p per container to fund the direct operational costs of the scheme during the observatory period while this reduces significantly to an average of £25.9 million a year or 1.5p per container during steady state operations.

4.38 It should be noted that while the Scheme Administrator is unable to recognise the net benefit of unredeemed deposits during the observatory period, it will accumulate a large cash balance which can be observed below in the Cash Flow Implications section.

Figure 13: Summary of Average Annual Revenue and Expenditure of Scheme Administrator under Observatory Period (Year 0 to Year 5)

Figure 13: Summary of Average Annual Revenue and Expenditure of Scheme Administrator under Observatory Period (Year 0 to Year 5)

Figure 14: Summary of Average Annual Revenue and Expenditure of Scheme Administrator under Steady State (Year 6 to Year 9)

Figure 14: Summary of Average Annual Revenue and Expenditure of Scheme Administrator under Steady State (Year 6 to Year 9)

Note: the variance between total revenues and total expenditure reflects approximately £2 million of interest income which appears below the gross margin line, however, is included in the calculation of the producer fee to ensure all scheme income and expenses are reflected.

Table 33: Ten-Year Revenue and Expenditure Summary

Table 33: Ten-Year Revenue and Expenditure Summary

4.39 The key points arising from the profit and loss analysis:

1. Operational scheme costs are expected to ramp up between Year 0 and Year 1 in anticipation of Go-Live, including significant spend on campaigning efforts. As no income is received from deposits during Year 0, costs will need to be covered by the producer fee.

2. Deposits received in Year 1 are higher, as this includes the initial supply of containers that will stock the supply chain at the start of Year 1.

3. The producer fee is calculated to offset the expenses in operating the scheme, including debt service payments. On the assumption that the Scheme Administrator will be unable to recognise the benefit of 'never to be redeemed' deposits until Year 6, the producer fee is significantly higher from Year 1 to Year 5. The producer fee approximately halves in value once the Scheme Administrator can recognise the 'never to be redeemed deposits' impact. The forecast average fee for Year 0 to Year 5 is ~£48 million a year or 3.3p/container, for Year 6 to Year 9. This reduces to ~£26 million a year or 1.5p/container (which is considered to be the steady state position for the producer fee).

4. As identified above, the costs of operating the scheme need to be funded by the sale of materials and producer fee only in the early years as the Scheme Administrator builds a sufficient evidence base for inclusion of 'never to be redeemed deposits' in its profit and loss. A summary of the impact of the deposit flows and provision on the balance sheet that are recognised in the profit and loss are set out below:

summary of the impact of the deposit flows and provision on the balance sheet that are recognised in the profit and loss

5. The handling fee is currently set at 1.5p (manual) and 3.1p (auto) per container resulting in an average handling fee of approximately £48 million a year.

6. The Scheme Administrator builds up significant cash balances in first five years earning (1% a year) interest. Interest paid is in relation to the borrowing for the asset purchases in Year 0.

7. The producer fee is set to provide a profit after tax matched to the principal repayments on borrowing.

4.6 Impact on Balance Sheet

4.40 The proposed capital expenditure is predicted to have the following impact on the Scheme Administrator's balance sheet (see Table 34)

Table 34: Summary Balance Sheet

Table 34: Summary Balance Sheet

4.41 The key points arising from the balance sheet analysis are:

1. £27.6 million investment in assets in Year 0 (counting centres, equipment and IT). A further £8 million investment in Year 8 to replace the equipment which has a useful life of seven years.

2. It is expected that there will be deposits not redeemed from the beginning of the scheme which results in a cash inflow. From Year 6 this cash benefit is recognised by way of the net difference between revenue from producers (deposits in) and expenditure paid to retailers (deposits out) and this is used to part fund the scheme. Prior to Year 6 as explained in the income and expenditure section, it is assumed this cash benefit cannot be recognised as a net revenue in income and expenditure as the Scheme Administrator may not have sufficient evidence to justify this. This results in the significant build-up of cash balances in the first five years. The Scheme Administrator may be able to justify the recognition of the net revenue in the income and expenditure account at an earlier date and this would reduce the level of cash balances being built up. However, this will be examined in more detail at FBC Stage 2.

3. A working capital assumption of 30 days has been assumed for both the trade debtors and trade creditors as an initial assumption.

4. The initial asset purchase is assumed to be financed by commercial borrowing which is repaid over a ten-year period.

5. The deposit liability fund is a provision to recognise that potential containers are still out in the public domain which could be returned and, therefore, remain a liability to the Scheme Administrator. This is built up over the first five years as it is assumed during this period the Scheme Administrator has to assume that all deposits will remain repayable. It is only by Year 6 that the Scheme Administrator will have built a sufficient evidence base to justify that there is an element of this liability that can be written off. A prudent assumption that this fund remains stable from Year 6 has been assumed. There may, however, be sufficient evidence for this to be written down which would result in the release of a benefit to the income and expenditure account.

4.7 Cash flow Implications

4.42 Table 35 summarises the impact on the projected cash flow position of the Scheme Administrator as a result of the preferred option.

Table 35: Cash flow implications

Table 35: Cash flow implications

4.43 The key points arising from the cash flow analysis are:

1. During Year 0 to Year 5, the producer fee is set at a higher level to recover the costs of the scheme (including debt service) prior to the recognition of any net benefit from unredeemed deposits as explained in the income and expenditure and balance sheet sections. This will be examined further as part of the next stage of work to identify whether this cash can be released earlier, or whether there are alternative routes to avoid a higher producer fee in the early years without impacting on the liquidity or solvency of the scheme.

2. Initial investment is funded through commercial borrowing - this will also be further examined as part of the next stage to identify the most efficient route for financing the investment requirements. This could include the Scheme Administrator paying an operator fee which would negate the requirement for the majority of the upfront investment, or ramping up investment over the first couple of years as opposed to the full amount in Year 0.

3. The replacement of equipment required in Year 8 is assumed to be funded through the cash balances as opposed to any further borrowing.

4. The Scheme Administrator is indicating a cash balance of around £200 million by Year 6 as a result of the higher producer fee in the earlier years. The next stage will look at alternative routes to make better use of this cash balance, either in the early years or from Year 6 where it could be used to minimise or mitigate the producer fee for a period of time.

4.8 Sensitivities

4.44 In addition to the assessment in sections 4.5 to 4.7, sensitivities have been undertaken to assess the impact of varying key assumptions as modelled in the base case assumptions. Given the producer fee is set on a cost-recovery basis (balancing item), the value of this line item will shift to absorb adverse movements that increase the cost base in addition to debt-service on the commercial loan. As a result, the sensitivity analysis measures the impact to the producer fee where variables are altered as opposed to the net scheme position. The producer fee under the base case is, on average, £48.4 million or 3.3p per container under the observatory period which reduces to £25.9 million or 1.5p per container under steady state operations. For the purposes of undertaking the sensitivity analysis, which is concerned largely with the directional change and identifying the variables which have the greatest impact on the producer fee, the average producer fee under steady state has been extrapolated over the ten-year model and has been utilised as the baseline for measurement.

4.45 The sensitivities that have been applied, including a brief description and resulting change in the producer fee, are summarised in Table 36 below. All sensitivities have been run in isolation to understand the specific impacts of the considered variable.

Table 36: Sensitivities

Sensitivity

Description

Current assumption

Sensitised assumption

Sensitised average producer fee a year

Change against base case producer fee (%)

Increase in handling fee by 10%

The handling fee reflects the largest driver within the Scheme Administrator's cost base, approximately, 65%. The sensitivity takes the calculated handling fee across all return points and increases this amount by 10%. The handling fee will be subject to negotiation and commercial discussions with retailers.

On average, £48.4 million per year

On average, £53.2 million per year

£25.8 million per year.

(1.6p/ct)

Increase by 19%

Increase in volume of DRS material flowing through automatic return point (Return Point 3) by 5%

The volume of DRS material that flows through each return point impacts the logistics cost and handling fee cost elements.

85% Return Point 3

15% Return Points 1,2 and 4

90% Return Point 3

10% Return Points 1,2 and 4

£21.2 million per year

(1.4p/ct)

Decrease by 17%

Decrease in sale of material revenue rates by 10%

Each sale of material £/tonne rate is applied to its respective volume of material to calculate forecast revenue. Sale of materials rates can be subject to price volatility in international/ domestic markets for each material type.

PET - £200/tonne

Aluminium and steel - £1,300/ tonne

Glass (flint) - £17/tonne

Glass (green) - £6/tonne

Glass (brown) - £12/tonne

PET - £180/tonne

Aluminium and steel - £1,170/ tonne

Glass (flint) - £15/tonne

Glass (green) - £5.6/tonne

Glass (brown) - £11/tonne

£23.3 million per year

(1.5p /ct)

Increase by 8.0 %

Increase in logistics fee (manual and automatic) by 10%

Each logistics £/tonne rate is applied to the respective volume of material that is forecast to be collected through the relevant return point channel i.e. 85% of material is expected to be handled through an automatic return point, whilst 15% is expected to be handled through a manual return point.

Logistics fee for automatic handling - £95/tonne

Logistics fee for manual handling - £150/tonne

Logistics fee for automatic handling - £105/tonne

Logistics fee for manual handling - £165/tonne

£24.7 million per year

(1.6p/ct)

Increase by 14.4%

Contact

Email: timothy.chant@gov.scot

Back to top